Discrepancy between Contract Documents. 1.4.1 In any event MWC determines that a discrepancy exists any of the Contract Documents or in the event the CMC argues that such contradiction exists, MWC shall instruct the order of precedence to be applied. 1.4.2 The CMC shall be bound to its Proposal, as accepted by MWC. For the avoidance of doubt, in case of a discrepancy between the CMC’s Proposal and any of eh remaining Contract Documents, MWC may determine which documents or provisions, or part thereof, shall prevail.
Appears in 2 contracts
Sources: Contract for the Appointment of a Construction Management Company, Contract for the Appointment of a Construction Management Company
Discrepancy between Contract Documents. 1.4.1 In any event MWC determines that a discrepancy exists any of the Contract Documents or in the event the CMC Supplier argues that such contradiction exists, then MWC shall instruct the order of precedence to be appliedprecedence.
1.4.2 1.4.1. The CMC Supplier shall be bound to its Proposal, as accepted by MWC. For the avoidance of doubt, in case of a discrepancy between the CMCSupplier’s Proposal and any of eh remaining Contract Documents, MWC may determine which documents or provisions, or part thereof, shall prevail.
Appears in 2 contracts
Sources: Contract for the Design, Manufacture, Supply, Installation and Commissioning of Electrically Operated Pumping Units and Associated Services, Contract for the Design, Manufacture, Supply, Installation and Commissioning of Electrically Operated Pumping Units and Associated Services