Drawings Submitted. Contractor shall not deviate from Contractor Drawings and Manuals submitted to and accepted by Company or issued by Contractor as approved for construction, except with the prior written consent of Company, which consent shall not be unreasonably withheld or delayed. Notwithstanding the foregoing in this Section 15.4, Contractor may make minor deviations in order to accommodate the economical and timely performance of the Work, and to enhance safety and quality outcomes, provided that such minor deviations do not affect the Contractor’s compliance with this Contract and the Specifications. Any such deviations will be incorporated into the final version of the drawings delivered to Company.
Appears in 2 contracts
Sources: Engineering, Procurement and Construction Contract (Chugach Electric Association Inc), Engineering, Procurement and Construction Contract (Chugach Electric Association Inc)