Common use of Early Warning Clause in Contracts

Early Warning. 15.1.1 The Operator shall give an early warning by notifying the DEA by notice as soon as the Operator becomes aware of any matter which could potentially affect the Operator’s ability to perform the CCS Activities in accordance with the Contract. Either Party may call in a meeting regarding the early warning if it is deemed necessary.

Appears in 6 contracts

Sources: Contract on Subsidy for Carbon Capture, Transport and Storage, Contract on Subsidy for Carbon Capture, Transport and Storage, Contract on Subsidy for Carbon Capture, Transport and Storage

Early Warning. 15.1.1 19.1.1 The Operator shall give an early warning by notifying the DEA by notice as soon as the Operator becomes aware of any matter which could potentially affect the Operator’s ability to perform the CCS Activities in accordance with the Contract. Either Party may call in a meeting regarding the early warning if it is deemed necessary.

Appears in 3 contracts

Sources: Contract on Subsidy for Negative Emissions Carbon Capture, Transport and Storage, Contract on Subsidy for Negative Emissions Carbon Capture, Transport and Storage, Contract on Subsidy for Negative Emissions Carbon Capture, Transport and Storage

Early Warning. 15.1.1 20.1.1 The Operator shall give an early warning by notifying the DEA by notice as soon as the Operator becomes aware of any matter which could potentially affect the Operator’s ability to perform the CCS Activities in accordance with the Contract. Either Party may call in invite for a meeting regarding the early warning if it is deemed necessary.

Appears in 1 contract

Sources: Contract on Subsidy for Carbon Capture, Transport and Storage

Early Warning. 15.1.1 20.1.1 The Operator shall give an early warning by notifying the DEA by notice as soon as the Operator becomes aware of any matter which could potentially affect the Operator’s ability to perform the CCS Activities in accordance with the Contract. Either Party may call in a meeting regarding the early warning if it is deemed necessary.

Appears in 1 contract

Sources: Contract on Subsidy for Carbon Capture, Transport and Storage

Early Warning. 15.1.1 20.1.1 The Operator shall give an early warning by notifying the DEA by notice as soon as the Operator becomes aware of any matter which could potentially affect the Operator’s ability to perform the CCS Activities in accordance with the Contract. Either Party may call in ininvite for a meeting regarding regard- ing the early warning if it is deemed necessary.

Appears in 1 contract

Sources: Contract on Subsidy for Carbon Capture, Transport and Storage