EVENTS OF DEFAULTS AND CONSEQUENCES Clause Samples
POPULAR SAMPLE Copied 1 times
EVENTS OF DEFAULTS AND CONSEQUENCES. 9.1. Subject to the Force Majeure clause, the Promoter shall be considered under a condition of Default, in the following events:
(i) Promoter fails to provide ready to move in possession of the Apartment to the Allottee within the time period specified in Clause 7.1 or fails to complete the Real Estate Project within the stipulated time disclosed at the time of registration of the Project with the Authority. For the purpose of this Clause 'ready to move in possession' shall mean that the Said Apartment shall be in a habitable condition which is complete in all respects including the provision of all specifications as specified in Schedule D of this Agreement, and for which completion certificate, has been issued by the competent authority;
(ii) Discontinuance of the Promoter's business as a developer on account of suspension or revocation of his registration under the provisions of the Act or the rules or regulations made thereunder.
9.2. In case of Default by Promoter under the conditions listed above, Allottee is entitled to the following:
(i) Stop making further payments to Promoter as demanded by the Promoter. If the Allottee stops making payments the Promoter shall correct the situation by completing the construction milestones and only thereafter the Allottee be required to make the next payment without any interest; or
(ii) The Allottee shall have the option of terminating the Agreement in which case the Promoter shall be liable to refund the entire money paid by the Allottee under any head whatsoever towards the purchase of the apartment, along with interest at the rate prescribed in the Rules within forty-five days of receiving the termination notice subject to allottee registering the deed of cancellation in respect of the Said Apartment and Appurtenances; Provided that where an Allottee does not intend to withdraw from the Project or terminate the Agreement, he shall be paid, by the promoter, interest at the rate prescribed in the Rules, for every month of delay till the handing over of the possession of the Said Apartment, which shall be paid by the Promoter to the Allottee within forty-five days of it becoming due.
9.3. The Allottee shall be considered under a condition of Default, on the occurrence of the following events:
(i) In case the Allottee fails to make payment to the Promoter as per the Payment Plan annexed hereto, despite having been issued notice in that regard, the Allottee shall be liable to pay interest to the Promoter on the u...
EVENTS OF DEFAULTS AND CONSEQUENCES. Subject to the Force Majeure clause, the Promoter shall be considered under a condition of Default, in the following events:
(i) Promoter fails to provide ready to move in possession of the [Apartment/Plot] to the Allottee within the time period specified. For the purpose of this clause, 'ready to move in possession' shall mean that the apartment shall be in a habitable condition which is complete in all respects;
(ii) Discontinuance of the Promoter's business as a developer on account of suspension or revocation of his registration under the provisions of the Act or the rules or regulations made thereunder. In case of Default by Promoter under the conditions listed above, Allottee is entitled to the following:
(i) Stop making further payments to Promoter as demanded by the Promoter. If the Allottee stops making payments, the Promoter shall correct the situation by completing the construction milestones and only thereafter the Allottee be required to make the next payment without any penal interest; or
(ii) The Allottee shall have the option of terminating the Agreement in which case the Promoter shall be liable to refund the entire money paid by the Allottee under any head whatsoever towards the purchase of the apartment, along with interest at the rate specified in the Rules within forty-five days of receiving the termination notice: Provided that where an Allottee does not intend to withdraw from the project or terminate the Agreement, he shall be paid, by the promoter, interest at the rate specified in the Rules, for every month of delay till the handing over of the possession of the [Apartment/Plot]. The Allottee shall be considered under a condition of Default, on the occurrence of the following events:
(i) In case the Allottee fails to make payments for consecutive demands made by the Promoter as per the Payment Plan annexed hereto, despite having been issued notice in that regard the allottee shall be liable to pay interest to the promoter on the unpaid amount at the rate specified in the Rules.
(ii) In case of Default by Allottee under the condition listed above continues for a period beyond consecutive months after notice from the Promoter in this regard, the Promoter shall cancel the allotment of the [Apartment/ Plot] in favour of the Allottee and refund the amount money paid to him by the allottee by deducting the booking amount and the interest liabilities and this Agreement shall thereupon stand terminated.
EVENTS OF DEFAULTS AND CONSEQUENCES. 9.1 Subject to the Force Majeure clause, the Promoter shall be considered under a condition of Default, in the following events:
(i) Promoter fails to provide ready to move in possession of the [Apartment/Plot] to the Allottee within the time period specified in para 7.1 or fails to complete the project within the stipulated time disclosed at the time of registration of the project with the Authority. For the purpose of this para, 'ready to move in possession' shall mean that the apartment shall be in a habitable condition which is complete in all respects including the provision of all specifications, amenities and facilities, as agreed to between the parties, and for which occupation certificate and completion certificate, as the case may be, has been issued by the competent authority;
(ii) Discontinuance of the Promoter’s business as a developer on account of suspension or revocation of his registration under the provisions of the Act or the rules or regulations made the re under.
9.2 In case of Default by Promoter under the conditions listed above, Allottee is entitled to the following:
(i) Stop making further payments to Promoter as demanded by the Promoter. If the Allottee stops making payments, the Promoter shall correct the situation by completing the construction milestones and only thereafter the Allottee be required to make the next payment without any interest; or
(ii) The Allottee shall have the option of terminating the Agreement in which case the Promoter shall be liable to refund the entire money paid by the Allottee under any head whatsoever towards the purchase of the apartment, along with interest at the rate prescribed in the Rules within forty-five days of receiving the termination notice: Provided that where an Allottee does not intend to withdraw from the project or terminate the Agreement, he shall be paid, by the promoter, interest at the rate prescribed in the Rules, for every month of delay till the handing over of the possession of the [Apartment/Plot], which shall be paid by the promoter to the allottee within forty-five days of it becoming due.
9.3 The Allottee shall be considered under a condition of Default, on the occurrence of the following events:
(i) In case the Allottee fails to make payments for consecutive demands made by the Promoter as per the Payment Plan annexed hereto, despite having been issued notice in that regard the allottee shall be liable to pay interest to the promoter on the unpaid amount at the rate pre...
EVENTS OF DEFAULTS AND CONSEQUENCES. 9.1 Subject to the Force Majeure clause, the CGEWHO shall be considered under a condition of Default, in the following events:
(i) CGEWHO fails to provide ready to move in possession of the [Apartment/Plot] to the Allottee within the time period specified in para 7.1 or fails to complete the project within the stipulated time disclosed at the time of registration of the project with the Authority. For the purpose of this para, ‘ready to move in possession’ shall mean that the apartment shall be in a habitable condition which is complete in all respects including the provision of all specifications, amenities and facilities, as agreed to between the parties, and for which occupation certificate and completion certificate, as the case may be, has been issued by the competent authority.
(ii) Discontinuance of the CGEWHO’s business as a developer on account of suspension or revocation of his registration under the provisions of the Act or the rules or regulations made thereunder.
9.2 In case of Default by CGEWHO under the conditions listed above, Allottee is entitled to the following:
(i) Stop making further payments to CGEWHO as demanded by the CGEWHO. If the Allottee stops making payments, the CGEWHO shall correct the situation by completing the construction milestones and only thereafter the Allottee be required to make the next payment without any penal interest; or
(ii) The Allottee shall have the option of terminating the Agreement in which case the CGEWHO shall be liable to refund the entire money paid by the Allottee under any head whatsoever towards the purchase of the dwelling unit, along with simple interest @10% p.a. and also all the components of Total Price excluding GST as defined in Clause1.2 within forty-five days of receiving the termination notice: Provided that where an Allottee does not intend to withdraw from the project or terminate the Agreement, he shall be paid, by the CGEWHO, simple interest @10% p.a., for every month of delay till the handing over of the possession of the dwelling unit. Which shall be paid by the CGEWHO to the allottee within Forty-five days of it becoming due.
9.3 The Allottee shall be considered under a condition of Default, on the occurrence of the following events:
(i) In case the Allottee fails to make payments for consecutive demand made by CGEWHO as per the payment plan annexed hereto, despite having been issued notice in that regard, the allottee shall be liable to pay interest to the CGEWHO on the unpaid am...
EVENTS OF DEFAULTS AND CONSEQUENCES. 9.1. Subject to the Force Majeure clause, the Promoter shall be considered under a condition of Default, in the following events:
(i) Promoter fails to provide ready to move in possession of the Apartment to the Allottee within the time period specified in para 7.1 or fails to complete the project within the stipulated time disclosed at the time of registration of the project with the authority. For the purpose of this para ‘ready to move in possession’ shall mean that the apartment shall be in a habitable condition which is complete in all respects including the provision of all specification, amenities and facilities, as agreed to between the parties, and for which occupation certificate and completion certificate, as the case may be, has been issued by the competent authority;
(ii) Discontinuance of the Promoter’s business as a developer on account of suspension or revocation of his registration under the provisions of the Act or the rules or regulations made thereunder.
9.2. In case of Default by Promoter under the conditions listed above, Allottee is entitled to the Following:
(i) Stop making further payments to Promoter as demanded by the Promoter. If the Allottee stops making payments the Promoter shall correct the situation by completing the construction milestones and only thereafter the Allottee be required to make the next payment without any interest; or
(ii) The Allottee shall have the option of terminating the Agreement in which case the Promoter shall be liable to refund the entire money paid by the Allottee under any head whatsoever towards the purchase of the apartment, along with interest at the rate prescribed in the Rules within forty-five days of receiving the termination notice; Provided that where an Allottee does not intend to withdraw from the project or terminate the Agreement, he shall be paid, by the promoter, interest at the rate prescribed in the Rules, for every month of delay till the handing over of the possession of the (Apartment/Plot), which shall be paid by the promoter to the Allottee within forty-five days of it becoming due.
9.3. The Allottee shall be considered under a condition of Default, on the occurrence of the following Events:
(i) In case the Allottee fails to make payments for consecutive demands made by the Promoter as per the Payment plan annexed hereto, despite having been issued notice in that regard the Allottee shall be liable to pay interest to the promoter on the unpaid amount at the rate prescribed i...
EVENTS OF DEFAULTS AND CONSEQUENCES. 9.1 Subject to the Force Majeure clause, the Promoter shall be considered under a condition of default, in the following events, namely:-
(i) The Promoter fails to provide ready to move in possession of the Apartment /Flat to the Allottee(s) within the time period specified in Term No. 7.1 above in this Agreement or fails to complete the Project within the stipulated time disclosed at the time of registration of the Project with the Authority. For the purpose of this clause, 'ready to move in possession' shall mean that the Apartment or Flat shall be in a habitable condition which is complete in all respects including the provision of all specifications, amenities and facilities, as agreed to between the parties, and for which occupation certificate and completion certificate, as the case may be, has been issued by the competent authority;
(ii) Discontinuance of the Promoter's business as a developer on account of suspension or revocation or expiry of his registration under the provisions of the Act or the rules or regulations made thereunder.
9.2 In case of default by the Promoter under the conditions listed above, Allottee(s) is entitled to the following:-
(i) Stop making further payments to the Promoter as demanded by the Promoter. If the Allottee(s) stops making payments, the Promoter shall correct the situation by completing the construction/ development milestones and only thereafter the Allottee(s) be required to make the next payment without any interest; or
(ii) The Allottee(s) shall have the option of terminating the Agreement in which case the Promoter shall be liable to refund the entire money paid by the Allottee(s) under any head whatsoever towards the purchase of the Apartment, along with interest within forty-five days of receiving the termination notice: Provided that where an Allottee(s) does not intend to withdraw from the Project or terminate the Agreement, he shall be paid, by the Promoter, interest for the period of delay till the handing over of the possession of the Apartment/ Plot, which shall be paid by the Promoter to the Allottee within forty-five days of it becoming due.
9.3 The Allottee(s) shall be considered under a condition of default, on the occurrence of the following events:
(i) In case the Allottee(s) fails to make payments for -------------- consecutive demands made by the Promoter as per the payment plan stated above, despite having been issued notice in that regard, the Allottee(s) shall be liable to pay interest to ...
EVENTS OF DEFAULTS AND CONSEQUENCES. Subject to the Force Majeure clause, the Promoter shall be considered under a condition of Default, in the following events:
(i) Promoter fails to provide ready to move in possession of the [Apartment/Plot] to the Allottee within the time period specified in para 7.1 or fails to complete the project within the stipulated time disclosed at the time of registration of the project with the Authority. For the purpose of this para 'ready to move in possession’ shall mean that the apartment shall be in a habitable condition which is complete in all respects including the provision of all specifications, amenities and facilities, as agreed to between the parties, and for which occupation certificate and completion certificate, as the case may be, has been issued by the competent authority;
(ii) Discontinuance of the Promoter's business as a developer on account of suspension or revocation of his registration under the provisions of the Act or the rules or regulations made thereunder. In ease of Default by Promoter under the conditions listed above, Allottee is entitled to the following:
(i) Stop making further payments to Promoter as demanded by the Promoter. If the Allottee stops making payments the Promoter shall correct the situation by completing the construction milestones and only thereafter the the Allottee be required to make the next payment without any interest; or
(ii) The Allottee shall have the option of terminating the Agreement in which case the Promoter shall be liable to refund the entire money paid by the Allottee under any head whatsoever towards the purchase of the apartment, along with interest at the rate prescribed in the Rules within forty-five days of receiving the termination notice; Provided that where an Allottee does not intend to withdraw from the project or terminate the Agreement, he shall be paid, by the promoter, interest at the rate prescribed in the Rules, for every month of delay till the handing over of the possession of the (Apartment/Plot), which shall be paid by the promoter to the allottee within forty- five days of it becoming due. The Allottee shall be considered under a condition of Default, on the occurrence of the following events:
(i) Incase the Allottee fails to make payments for consecutive demands made by the Promoter as per the Payment Plan annexed hereto, despite having been issued notice in that regard the allottee shall be liable to pay interest to the promoter on the unpaid amount at the rate prescribed in t...
EVENTS OF DEFAULTS AND CONSEQUENCES. 9.1 Subject to the Force Majeure clause, the Promoter shall be considered under a condition of Default, in the following events:
(i) The Promoter fails to provide ready to move in possession of the Apartment to the Allottee within the time period specified in para 7.1 or fails to complete the Project within the stipulated time disclosed at the time of registration of the Project with the Authority. For the purpose of this para, ‘ready to move in possession’ shall mean that the Apartment shall be in a habitable condition which is complete in all respects including the provision of all specifications, amenities and facilities (except the Club facilities, which will be complete on completion of all the Phases of the Luxury Zone of the Complex), as agreed to between the parties, and for which Completion Certificate or Partial Completion Certificate, as the case may be, has been issued by the Competent Authority;
(ii) Discontinuance of the Promoter’s business as a developer on account of suspension or revocation of its registration under the provisions of the Act or the rules or regulations made thereunder.
9.2 In case of Default by the Promoter under the conditions listed above, the Allottee is entitled to the following:
(i) Stop making further payments to the Promoter as demanded by the Promoter If the Allottee stops making payments, the Promoter shall correct the situation by completing the construction milestones and only thereafter the Allottee be required to make the next payment without any interest; or
(ii) The Allottee shall have the option of terminating this Agreement in which case the Promoter shall be liable to refund the entire money paid by the Allottee under any heads whatsoever towards the purchase of the Apartment, along with interest at the rate prescribed in the Rules within 45 (forty-five) days of receiving the termination notice: Provided that where an Allottee does not intend to withdraw from the Project or terminate the Agreement, he shall be paid, by the Promoter, interest at the rate prescribed in the Rules, for every month of delay till the handing over of the possession of the Apartment, which shall be paid by the Promoter to the Allottee within 45 (forty-five days) of it becoming due.
9.3 The Allottee shall be considered under a condition of Default, on the occurrence of the following events:
(i) In case the Allottee fails to make payments for two consecutive demands made by the Promoter as per the Payment Plan annexed hereto, despi...
EVENTS OF DEFAULTS AND CONSEQUENCES. 9.1 Subject to the Force Majeure clause, the Promoter shall be considered under a condition of Default, in the Following events:
(i) Promoter fails to provide ready to move in possession of the Apartment to the Allottee within the time period specified in para 7.1or fails to complete the project within the stipulated time disclosed at the time of registration of the project with the Authority. For the purpose of this para ‘ready to move in possession’ shall mean that the apartment shall be in a habitable condition which is complete in all respects including the provision of all specifications, amenities and facilities, as agreed to between the parties, and for which Occupation Certificate and Completion Certificate, as the case may be has been issued by the Competent Authority.
(ii) Discontinuance of the Promoter’s business as a developer on account of suspension or revocation of his registration under the provisions of the Act or the rules or regulations made thereunder.
9.2 In case of Default by Promoter under the conditions listed above, Allottee is entitled to the following:
(i) Stop making further payments to Promoter as demanded by the Promoter. If the Allottee stops making payments the Promoter shall correct the situation by completing the construction milestones and only thereafter the Allottee be required to make the next payment without any interest; or
EVENTS OF DEFAULTS AND CONSEQUENCES. 9.1 Subject to the Force Majeure clause, the Promoter shall be considered under a condition of Default, in the following events:
i. Promoter fails to provide ready to move in possession of the [Apartment/Plot] to the Allottee within the time period specified in para 7.1 or fails to complete the project within the stipulated time disclosed at the time of registration of the project with the authority. For the purpose of this para ‘ready to move in possession’ shall mean that the apartment shall be in a habitable condition which is complete in all respects including the provision of all specification, amenities and facilities, as agreed to between the parties, and for which occupation certificate and completion certificate, as the case may be, has been issued by the competent authority.
ii. Discontinuance of the Promoter’s business as a developer on account of suspension or revocation of his registration under the provision of the Act or the rules or the rules or regulations made thereunder.