Excluded Cost Elements. It is the Department’s intent that the Design-Builder provide a turnkey solution for the implementation of the Project, and the Project Budget set herein has been developed based on such framework. The Design-Builder shall advance the Project in a manner consistent with the Project Budget with the understanding that only the following cost elements shall be excluded from the Project Budget set forth herein: a) 3rd Party Material Testing; b) 3rd Party Commissioning; c) 3rd Party Inspections; d) Costs of active DPR equipment; e) 3rd Party Plan Review; and f) Public Art.
Appears in 2 contracts
Sources: Design Build Agreement, Design Build Agreement
Excluded Cost Elements. It is the Department’s intent that the Design-Builder provide a turnkey solution for the implementation of the Project, and the Project Budget set herein has been developed based on such framework. The Design-Builder shall advance the Project in a manner consistent with the Project Budget with the understanding that only the following cost elements shall be excluded from the Project Budget set forth herein:
a) 3rd Party Material Testing;
b) 3rd Party Commissioning;
c) 3rd Party Inspections;
d) Costs of active DPR DOC equipment;
e) 3rd Party Plan Review; and
f) Public Art.
Appears in 1 contract
Sources: Design Build Agreement
Excluded Cost Elements. It is the Department’s intent that the Design-Builder provide a turnkey solution for the implementation of the Project, and the Project Budget set herein has been developed based on such framework. The Design-Builder shall advance the Project in a manner consistent with the Project Budget with the understanding that only the following cost elements shall be excluded from the Project Budget set forth herein:
a) 3rd Party Material Testing;
b) 3rd Party CommissioningInspections;
c) 3rd Party InspectionsCosts of active DOC equipment;
d) Costs of active DPR equipment;
e) 3rd Party Plan Review; and
fe) Public Art.
Appears in 1 contract
Sources: Design Build Agreement