Common use of Execution of Change Orders Clause in Contracts

Execution of Change Orders. Change Orders shall be signed by the CM/GC, ordinarily certified by the Design Professional, and approved by the Owner in accordance with the form of Change Order prescribed by the Owner in Section 7. No request for payment by the CM/GC for a Change Order shall be due, nor shall any such request appear on an Application for Payment, until the Change Order is executed by the Owner. In the event of emergency (see Paragraph 1.4.4) or significant impact to the Overall Project Schedule, the Owner shall direct the Change Order to proceed under a Force Account until the cost and time is resolved in the manner set forth in Paragraph 3.4.7.3 below.

Appears in 2 contracts

Sources: Construction Management Agreement, Construction Management Agreement

Execution of Change Orders. Change Orders shall be signed by the CM/GCDesign-Builder, ordinarily certified by the Design ProfessionalExecutive Administrator, and approved by the Owner in accordance with the form of Change Order prescribed by the Owner in Section 7Owner. No request for payment by the CM/GC Design-Builder for a Change Order shall be due, nor shall any such request appear on an Application for Payment, until the Change Order is executed by the Owner. In the event of emergency (see Paragraph Section 1.4.4) or significant impact to the Overall Project Schedule, the Owner shall direct the Change Order to proceed under upon a Force Account until the cost and time is resolved in the manner set forth in Paragraph 3.4.7.3 below.

Appears in 2 contracts

Sources: Design Build Contract, Construction Contract

Execution of Change Orders. Change Orders shall be signed by the CM/GCCMR, ordinarily certified by the Design Professional, and approved by the Owner in accordance with the form of Change Order prescribed by the Owner in Section 7Board. No request for payment by the CM/GC CMR for a Change Order shall be due, nor shall any such request appear on an Application for Payment, until the Change Order is executed by the OwnerBoard, and if applicable, for any Change Order that exceeds $50,000, upon approval by the Board. In the event of emergency (see Paragraph See Section 1.4.4) or significant impact to the Overall Project Schedule, the Owner Board shall direct the Change Order to proceed under upon a Force Account until the cost and time is resolved in the manner set forth in Paragraph Section 3.4.7.3 below.belo

Appears in 2 contracts

Sources: Construction Management at Risk Agreement, Construction Management at Risk Agreement

Execution of Change Orders. Change Orders shall be signed by the CM/GCCMR, ordinarily certified by the Design Professional, and approved by the Owner in accordance with the form of Change Order prescribed by the Owner in Section 7Board. No request for payment by the CM/GC CMR for a Change Order shall be due, nor shall any such request appear on an Application for Payment, until the Change Order is executed by the OwnerBoard, and if applicable, for any Change Order that exceeds $50,000, upon approval by the Board. In the event of emergency (see Paragraph See Section 1.4.4) or significant impact to the Overall Project Schedule, the Owner Board shall direct the Change Order to proceed under upon a Force Account until the cost and time is resolved in the manner set forth in Paragraph Section 3.4.7.3 below.:

Appears in 1 contract

Sources: Construction Management at Risk Agreement

Execution of Change Orders. Change Orders shall be signed by the CM/GC, ordinarily certified by the Design Professional, and approved by the Owner in accordance with the form of Change Order prescribed by the Owner in (See Section 7, Forms). No request for payment by the CM/GC for a Change Order shall be due, nor shall any such request appear on an Application for Payment, until the Change Order is executed by the Owner. In the event of emergency (see Paragraph Section 1.4.4) or significant impact to the Overall Project Schedule, the Owner shall direct the proposed Change Order to proceed under a Force Account authorization until the cost and time is resolved in the manner set forth in Paragraph Section 3.4.7.3 below.

Appears in 1 contract

Sources: Construction Management Agreement