Extension of Commercial Operation Date Sample Clauses

Extension of Commercial Operation Date. If Seller is unable to achieve Commercial Operation by the Outside Commercial Operation Date by reason of Force Majeure, then upon Notice to Buyer, Seller may extend the Outside Commercial Operation Date without payment or other penalty on a Day-for-Day basis for each Day of delay caused by reason of Force Majeure.
Extension of Commercial Operation Date. If Seller is unable to achieve Commercial Operation by the Outside32Target33 Commercial Operation Date by reason of Force Majeure, then upon Notice to Buyer, Seller may extend the Outside34Target35 Commercial Operation Date without payment or other penalty on a Day-for-Day basis for each Day of delay caused by reason of Force Majeure.36, such extension not to exceed the 37Outside38 Commercial Operation Date, which is subject to the termination provisions set forth in Section 15.2.39 5. Project Costs, Regulatory Review and Monthly Contract Price.
Extension of Commercial Operation Date 

Related to Extension of Commercial Operation Date

  • Commercial Operation Date 6.4.1 The SPV shall ensure that the Project Commercial Operation Date is achieved on or prior to the Scheduled Commercial Operation Date. The SPV shall provide a written notice to MSEDCL at least 30 (thirty) days in advance intimating MSEDCL of the proposed date on which the Commercial Operation Date of a Unit or the Project is proposed to be achieved. 6.4.2 If the Commercial Operation Date for the Units having a capacity equivalent to at least 75% (seventy five percent) of the Contracted Capacity is achieved before the Scheduled Commercial Operation Date, then all Units in respect of which the Commercial Operation Date has been achieved prior to the Scheduled Commercial Operation Date would be eligible for incentives as follows: (a) the Unit(s) injecting energy at 11 kV /22 kV shall be given an incentive of Rs. 0.25/ kWh; and (b) the Unit(s) injecting energy at 33 kV shall be given an incentive of Rs. 0.15/ kWh, for the power sold to MSEDCL for the first 3 (three) years from the Commercial Operation Date. To receive such incentives from MSAPL, which shall be over and above the Tariff, the SPV shall follow the process agreed to by the SPV under the Implementation Agreement. 6.4.3 It is hereby clarified that the aforementioned incentive shall not be available: (i) in respect of any Unit if the Commercial Operation Date for such Unit has not been achieved prior to the Scheduled Commercial Operation Date; and (ii) if the aggregate capacity of the Units for which the Commercial Operation Date has been achieved prior to Scheduled Commercial Operation Date is less than 75% (seventy five percent) of the Contracted Capacity. 6.4.4 In the event that Commercial Operation Date for any of the Units is achieved after the Scheduled Commercial Operation Date, the SPV shall be liable to pay Liquidated Damages as per the provisions set out below. 6.4.5 Without prejudice to any other rights of MSEDCL under this PPA, in case one or more Units of the SPV are unable to achieve Commercial Operation Date within a period of 2 (two) months from the Scheduled Commercial Operation Date, the capacity of such Units shall be annulled, and the Contracted Capacity shall be reduced to that extent. For Illustration: The Project has a Contracted Capacity of 100 MW and comprises of 10 Units of 10 MW each. If at the end of the aforementioned period of 14 (fourteen) months from the Effective Date, the SPV has achieved Commissioning for only 8 out of 10 Units, then the Contracted Capacity of the Project will stand reduced for the capacity of the 2 Units which have not been Commissioned, i.e. the Contracted Capacity will be 80 (100 (original Contracted Capacity)) – 10 (capacity of each Unit)*2 (number of Units not Commissioned).

  • Commercial Operation (i) On or before December 31, 2021, Interconnection Customer must demonstrate commercial operation of all generating units. Demonstrating commercial operation includes achieving Initial Operation in accordance with Section 1.4 of Appendix 2 to this ISA and making commercial sales or use of energy, as well as, if applicable, obtaining capacity qualification in accordance with the requirements of the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region.

  • Term Commencement Date For purposes of this Lease, the "Term Commencement Date" shall be defined as the earlier of (A) the first date on which Tenant occupies all or any part of the Premises for the conduct of business, or (B) fourteen (14) days after the date on which both of the following shall occur: (i) Landlord's Work shall be (or be deemed to be) substantially completed (notwithstanding the incompleteness of (x) so-called "punch list" items, (y) work to be undertaken by Landlord which does not materially impair Tenant's use of the Premises for the purposes allowed herein, and (z) finishes and exterior landscaping to the Property), and (ii) a certificate of occupancy has been (or is deemed to have been) issued with respect to the Premises (or the building inspector has (or is deemed to have) provided a verbal "sign off" on Landlord's Work and indicated that a certificate of occupancy will issue in due course). If Tenant (or any agent, employee or contractor of Tenant) causes any delay in the performance or substantial completion of Landlord's Work (including, without limitation, by failing to timely prepare the Construction Drawings), then Landlord's Work shall be deemed to have been substantially completed on the date that Landlord's Work would have been substantially completed but for such delay, and the certificate of occupancy for the Premises (or building inspector "sign off" as aforesaid) shall be deemed to have been issued (or provided) on the date it would have been issued (or provided) but for such delay. Landlord shall use reasonable efforts to substantially complete Landlord's Work by the date (as the same may be modified by Landlord at or prior to the time of its approval of the Construction Drawings as provided in the second paragraph of Section 10.22, the "Estimated Substantial Completion Date") which is ninety (90) days after Landlord's final approval of the Construction Drawings, but Tenant shall not have any claim against Landlord, and Landlord shall have no liability to Tenant, if Landlord's Work is not substantially completed by the Estimated Substantial Completion Date. Notwithstanding the foregoing, if Landlord fails to substantially complete Landlord's Work on or before the date which is sixty (60) days after the Estimated Substantial Completion Date due to Landlord's fault or neglect, then Tenant shall be entitled to a credit (offset) against Base Rent due and payable as of the Term Commencement Date in the amount of one (1) day of Base Rent for each day after the Estimated Substantial Completion Date that Landlord's Work shall not have been substantially completed.

  • DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION § 3.1 The date of commencement of the Work shall be: § 3.2 The Contract Time shall be measured from the date of commencement of the Work.

  • Extension of Commitment Termination Date The Borrower may, no more frequently than once each year by delivering written notice to the Managing Agents (with a copy to the Program Agent), request the Lenders to extend the Commitment Termination Date for an additional 364 days past the then applicable Commitment Termination Date, with such extension to become effective with respect to any Lender Group, as of the date one or more Committed Lenders having Commitments equal to 100% of such Lender Group’s Lender Group Limit shall in their sole discretion consent to such extension (the Lenders in such a Lender Group, “Extending Lenders”). Any such request shall be subject to the following conditions: (i) at no time will any Commitment have a term of more than 364 days and, if any such request would result in a term of more than 364 days, such request shall be deemed to have been made for such number of days so that, after giving effect to such extension on the date requested, such term will not exceed 364 days, (ii) none of the Lenders will have any obligation to extend any Commitment, (iii) any such extension of the Commitment Termination Date will be effective only upon the written agreement of at least one Committed Lender and the Borrower and (iv) any request for such extension shall be made at least sixty (60) days prior to the then current Commitment Termination Date. The Managing Agent for each applicable Committed Lender will respond to any such request within thirty (30) days (with a copy to the Paying Agent) but in any event no earlier than thirty (30) days prior to the then current Commitment Termination Date, provided that any Managing Agent’s failure to respond within such period shall be deemed to be a rejection of the requested extension.