Extension of the Guaranteed Dates. The Guaranteed Construction Start Date and the Guaranteed Commercial Operation Date shall, subject to notice and documentation requirements set forth below, be automatically extended on a day-for-day basis due to a Force Majeure Event for a period of up to one-hundred eighty (180) days on a cumulative basis (the “Development Cure Period”). Notwithstanding anything to the contrary, no extension shall be given under the Development Cure Period for a Force Majeure Event if the delay was due to Seller’s failure to take commercially reasonable actions to meet its requirements and deadlines or does not otherwise satisfy the requirements of a Force Majeure Event, including the notice and documentation requirements under Section 10.3.