Common use of Extension of the Guaranteed Dates Clause in Contracts

Extension of the Guaranteed Dates. The Guaranteed Construction Start Date and the Guaranteed Commercial Operation Date shall, subject to notice and documentation requirements set forth below, be automatically extended on a day-for-day basis due to a Force Majeure Event for a period of up to one-hundred eighty (180) days on a cumulative basis (the “Development Cure Period”). Notwithstanding anything to the contrary, no extension shall be given under the Development Cure Period for a Force Majeure Event if the delay was due to Seller’s failure to take commercially reasonable actions to meet its requirements and deadlines or does not otherwise satisfy the requirements of a Force Majeure Event, including the notice and documentation requirements under Section 10.3.

Appears in 2 contracts

Sources: Renewable Power Purchase Agreement, Renewable Power Purchase Agreement