Extension of Time for Completion of Project Commissioning. 10.4.1 Without prejudice to any other provisions of this Contract Agreement for and in respect of extension of time, the Contractor shall be entitled to extension of time in the Project Commissioning Schedule (the “Time Extension”) to the extent that completion of any Project Milestone is or will be delayed by any of the following, namely: a) Change of Scope (unless an adjustment to the Scheduled Project Commissioning Date has been agreed under Article13); b) occurrence of a Force Majeure Event; c) delay, impediment or prevention caused by or attributable to the Authority; and d) Any other cause or delay which entitles the Contractor to Time Extension in accordance with the provisions of this Contract Agreement.