Extent of Responsibility. The Construction Manager shall exercise reasonable care in performing its Preconstruction Services. The Owner and Architect shall be entitled to rely on, and shall not be responsible for, the accuracy, completeness, and timeliness of services and information furnished by the Construction Manager. The Construction Manager, however, does not warrant or guarantee estimates and schedules except as may be included as part of the Guaranteed Maximum Price. The Construction Manager is not required to ascertain that the Drawings and Specifications are in accordance with applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities, but the Construction Manager shall promptly report to the Architect and Owner any nonconformity discovered by or made known to the Construction Manager as a request for information in such form as the Architect may require.

Appears in 22 contracts

Sources: Standard Form of Agreement Between Owner and Construction Manager as Constructor, Guaranteed Maximum Price Amendment, Standard Form of Agreement Between Owner and Construction Manager as Constructor

Extent of Responsibility. The Construction Manager shall exercise reasonable care in performing its Preconstruction Services. The Owner preparing schedules and Architect shall be entitled to rely on, and shall not be responsible for, the accuracy, completeness, and timeliness of services and information furnished by the Construction Managerestimates. The Construction Manager, however, does not warrant or guarantee estimates and schedules except as may be included as part of the Guaranteed Maximum Price. The recommendations and advice of the Construction Manager concerning design alternatives and potential cost savings shall be subject to the review and approval of the Architect, Owner and the Owner's professional consultants. The Construction Manager is not required to ascertain that the Drawings and Specifications are in accordance with applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities, but the Construction Manager shall promptly report to the Architect and Owner any nonconformity discovered by by, or that reasonably should have been discovered by, or made known to the Construction Manager as a request for information in such form as the Architect may require.

Appears in 2 contracts

Sources: Standard Form of Agreement Between Owner and Construction Manager as Constructor, Standard Form of Agreement Between Owner and Construction Manager as Constructor

Extent of Responsibility. The Construction Manager shall exercise reasonable care in performing its Preconstruction Services. The Owner preparing schedules and Architect shall be entitled to rely on, and shall not be responsible for, the accuracy, completeness, and timeliness of services and information furnished by the Construction Manager. The Construction estima Manager, however, does not warrant or guarantee estimates and schedules except as may be included b Guaranteed Maximum Price. The recommendations and advice of the Construction Manage The Construction uded as part of the Guaranteed Maximum Pricencerning design alternatives shall be subject to the review and approval of the Owner and the Owner's professional consultants. The Construction Manager is not required to ascertain that the Drawings and Specifications are in accordance with applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities, but the Construction Manager shall promptly report to the Architect and Owner any nonconformity discovered by or made known to the Construction Manager as a request for information in such form as the Architect may require.

Appears in 1 contract

Sources: Standard Form of Agreement Between Owner and Construction Manager as Constructor

Extent of Responsibility. The Construction Manager shall exercise reasonable care in performing its Preconstruction Services. The Owner City and Architect shall be entitled to rely on, and shall not be responsible for, the accuracy, completeness, and timeliness of services and information furnished by the Construction Manager. The Construction Manager, however, does not warrant or guarantee estimates and schedules except as may be included as part of the Guaranteed Maximum Price. The Construction Manager is not required to ascertain that the Drawings and Specifications are in accordance with applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities, but the Construction Manager shall promptly report to the Architect and Owner City any nonconformity discovered by or made known to the Construction Manager as a request for information in such form as the Architect may require.

Appears in 1 contract

Sources: Construction Manager/General Contractor Agreement

Extent of Responsibility. The Construction Manager shall exercise reasonable care in performing its Preconstruction Services. The Owner and Architect shall be entitled to rely on, and shall not be responsible for, the accuracy, completeness, and timeliness of services and information furnished by the Construction Manager. The Construction Manager, however, does not warrant or guarantee estimates and schedules except as may be included as part of the Guaranteed Maximum Price. The Construction Manager is not required to ascertain that the Drawings and Specifications are in accordance with applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities, but the Construction Manager shall promptly report to the Architect and Owner any nonconformity discovered by or made known to the Construction Manager as a request for information in such form as the Architect may require.. DRAFT

Appears in 1 contract

Sources: Standard Form of Agreement Between Owner and Construction Manager as Constructor

Extent of Responsibility. The Construction Manager shall exercise reasonable care in performing its Preconstruction Services. The Owner and Architect shall be entitled to rely on, and shall not be responsible for, the accuracy, completeness, and timeliness of services and information furnished by the Construction Manager. The Construction Manager, however, does not warrant or guarantee estimates and schedules except as may be included as part of the Guaranteed Maximum Price. The Construction Manager is not required to ascertain that the Drawings and Specifications are in accordance with applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities, but the Construction Manager shall promptly report to the Architect and Owner any nonconformity discovered by or made known to the Construction Manager as a request for information in such form as the Architect may requirerequire and necessary changes may be accomplished by appropriate Modification to the Contract Documents.

Appears in 1 contract

Sources: Standard Form of Agreement Between Owner and Construction Manager as Constructor

Extent of Responsibility. The Construction Manager shall exercise at least reasonable care in performing its Preconstruction Services. The Owner and Architect shall be entitled to rely on, and shall not be responsible or liable for, the accuracy, completeness, and timeliness of services and information furnished by the Construction Manager. The Construction Manager, however, does not warrant or guarantee estimates and schedules except as may be included as part of the Guaranteed Maximum Price. The Construction Manager is not required to ascertain that the Drawings and Specifications are in accordance with applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities, but the Construction Manager shall promptly report to the Architect and Owner any nonconformity discovered by or made known to the Construction Manager as a request for information in such form as the Architect may require.

Appears in 1 contract

Sources: Standard Form of Agreement Between Owner and Construction Manager as Constructor

Extent of Responsibility. The Construction Manager shall exercise reasonable care in performing its Preconstruction Services. The Owner preparing schedules and Architect shall be entitled to rely on, and shall not be responsible for, the accuracy, completeness, and timeliness of services and information furnished by the Construction Managerestimates. The Construction Manager, however, does not warrant or guarantee estimates and schedules except as may be included as part of the Guaranteed Maximum Price. The recommendations and advice of the Construction Manager concerning the design alternatives and potential cost savings shall be subject to the review and approval of the Architect, Owner, and the Owner’s professional consultants. The Construction Manager is not required to ascertain that the Drawings and Specifications are in accordance with applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities, but the Construction Manager shall promptly report to the Architect and Owner any nonconformity discovered by by, or that reasonably should have been discovered by, or made known to the Construction Manager as a request for information in such form as the Architect may require.

Appears in 1 contract

Sources: Standard Form of Agreement Between Owner and Construction Manager as Constructor

Extent of Responsibility. The Construction Manager shall exercise reasonable care in performing its Preconstruction Services. The Owner and Architect shall be entitled to rely on, and shall not be responsible for, the accuracy, completeness, and timeliness of services and information furnished by the Construction Manager. The Construction Manager, however, does not warrant ram , schedule and nd or guarantee estimates and schedules except as may be included as part of the Guaranteed Maximum Price. The Construction Manager is not required to ascertain that the Drawings and Specifications are in accordance with applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities, but the Construction Manager shall promptly report to the Architect and Owner any nonconformity discovered by or made known to the Construction Manager as a request for information in such form as the Architect may require.

Appears in 1 contract

Sources: Standard Form of Agreement Between Owner and Construction Manager