Common use of Extreme Conditions Clause in Contracts

Extreme Conditions. The City reserves the right to refuse to accept power from and or disconnect any RRGS under extreme conditions which may adversely affect the City electric system or its customers, failure of the RRGS or customer to comply with any applicable rule or regulation and any condition which may pose a safety issue for the City, its customers or the RRGS owner. If the City chooses to exercise this option it shall make a reasonable effort to notify the customer when such conditions exist or are anticipated to exist, and to reconnect the system when the conditions no longer exist.

Appears in 2 contracts

Sources: Agreement for Parallel Connection of a Customer Owned Renewable Resource Generating System, Agreement for Parallel Connection of a Customer Owned Renewable Resource Generating System