Failure During Start-Up. Should any Equipment fail prior to Substantial Completion, spare parts may be withdrawn from Owner’s stock of operations and maintenance stores and the Equipment that failed returned to operating condition. Contractor shall at its cost promptly replace such withdrawn spare parts with new spare parts of the same type.
Appears in 2 contracts
Sources: General Services Agreement (Global Energy, Inc.), General Services Agreement (Global Energy, Inc.)
Failure During Start-Up. Should If any Equipment fail fails prior to Substantial Final Completion, spare parts may be withdrawn from Owner’s 's or Owner's stock of operations and maintenance stores and to repair the Equipment that failed returned to operating conditionfailed. Contractor shall at its cost shall promptly replace such all withdrawn spare parts with new spare parts of the same typetype made by the same manufacturer on or before Final Completion.
Appears in 1 contract
Sources: Engineering, Procurement and Construction Contract (Omega Protein Corp)