Field Directives. At no time shall Subcontractor proceed with work outside of the scope of the Work described in the Subcontract (and its Change Orders) without explicit written directive, given and signed by ▇▇▇▇▇’▇ project manager. Should Subcontractor perform any work outside of the scope of the Subcontract solely on the basis of verbal direction of anyone, such work shall be considered to be within the scope of the Subcontract, and payment for that work will be denied by ▇▇▇▇▇. Signatures on daily time tickets, or field work orders written by the Subcontractor shall not be considered to constitute explicit written directive given by the project manager.