Revenue Metering The Connecting Transmission Owner’s revenue metering will be located on the generator side of the 115kV breaker at the ▇▇▇▇▇ Solar Collector Substation and will consist of: • three (3) combination current/voltage transformer (“CT/VT”) units (manufacturer and model ABB/▇▇▇▇▇▇▇ KXM-550, GE Grid Solutions KOTEF ▇▇▇.▇▇, or other equivalent specified by Connecting Transmission Owner); and • one (1) revenue meter. The ratios of the CTs and VTs will be provided by Connecting Transmission Owner upon its review of the Interconnection Customer’s design documents. (Note: Connecting Transmission Owner’s revenue metering CTs and VTs cannot be used to feed the Interconnection Customer’s check meter.) SERVICE AGREEMENT NO. 2556
Check Meters Developer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check Connecting Transmission Owner’s meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this Agreement, except as provided in Article 7.4 below. The check meters shall be subject at all reasonable times to inspection and examination by Connecting Transmission Owner or its designee. The installation, operation and maintenance thereof shall be performed entirely by Developer in accordance with Good Utility Practice.
Mileage Measurement Where required, the mileage measurement for LIS rate elements is determined in the same manner as the mileage measurement for V&H methodology as outlined in NECA Tariff No. 4.
Power System Stabilizers The Developer shall procure, install, maintain and operate Power System Stabilizers in accordance with the requirements identified in the Interconnection Studies conducted for Developer’s Large Generating Facility. NYISO and Connecting Transmission Owner reserve the right to reasonably establish minimum acceptable settings for any installed Power System Stabilizers, subject to the design and operating limitations of the Large Generating Facility. If the Large Generating Facility’s Power System Stabilizers are removed from service or not capable of automatic operation, the Developer shall immediately notify the Connecting Transmission Owner and NYISO. The requirements of this paragraph shall not apply to wind generators.
Meters 7.1.1 For installation of Meters, Meter testing, Meter calibration and Meter reading and all matters incidental thereto, the SPD and SECI shall follow and be bound by the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, the Grid Code, as amended and revised from time to time. 7.1.2 The SPD shall bear all costs pertaining to installation, testing, calibration, maintenance, renewal and repair of meters at SPD’s side of Delivery Point. 7.1.3 In addition to ensuring compliance of the applicable codes, the SPD shall install Main & Check meters at the Delivery Point, along with Stand-by meter(s) as per the applicable Central/State regulations. 7.1.4 In case of pooling of multiple Projects, power from multiple Projects can be pooled at a Pooling Substation prior to the Delivery point and the combined power can be fed at Delivery point through a common transmission line from the Pooling Substation. In such cases, ABT compliant sub-meters as per relevant regulation/approval are also to be set up at pooling substation for individual projects in addition to the meters at Delivery Point as described in clause 7.1.3.