Common use of Final Completion Clause in Contracts

Final Completion. The point at which Substantial Completion has been achieved, all punch list items noted at Substantial Completion have been completed and all documents the Design-Builder is required to deliver to the Department as a condition to receiving final payment have been delivered.

Appears in 15 contracts

Sources: Design Build Agreement, Design Build Agreement, Design Build Agreement

Final Completion. The point at which Substantial Completion has been achieved, all punch list items noted at Substantial Completion have been completed and all documents the Design-Builder Contractor is required to deliver to the Department as a condition to receiving final payment have been deliveredpayment.

Appears in 10 contracts

Sources: Construction Agreement, Construction Agreement, Construction Agreement

Final Completion. The point at which Substantial Completion has been achieved, all punch list items noted at Substantial Completion have been completed and all documents the Design-Builder is required to deliver to the Department as a condition to receiving final payment have been deliveredreceived by the Department.

Appears in 7 contracts

Sources: Design Build Agreement, Design Build Agreement, Design Build Agreement

Final Completion. The point at which Substantial Completion has been achieved, all punch list items noted at Substantial Completion have been completed and all Project documents the Design-Builder is required to deliver to the Department as a condition to receiving final payment have been delivered.

Appears in 4 contracts

Sources: Design Build Agreement, Design Build Agreement, Design Build Agreement

Final Completion. The point at which Substantial Completion has been achieved, all punch list items noted at Substantial Completion have been completed and all documents the Design-Builder Contractor is required to deliver to the Department as a condition to receiving final payment have been delivered.

Appears in 4 contracts

Sources: Construction Management Agreement, Construction Management Agreement, Construction Management at Risk Services

Final Completion. The point at which Substantial Completion has been achieved, all punch list items noted at Substantial Completion have been completed and all documents the Design-Builder Construction Manager is required to deliver to the Department as a condition to receiving final payment have been delivered.

Appears in 4 contracts

Sources: Construction Management at Risk Agreement, Construction Management at Risk Agreement, Construction Management at Risk Agreement

Final Completion. The point at which Substantial Completion has been achieved, all punch list punchlist items noted at Substantial Completion have been completed and all documents the Design-Builder is required to deliver to the Department as a condition to receiving final payment have been delivered.

Appears in 4 contracts

Sources: Design Build Agreement, Design Build Agreement, Design Build Agreement

Final Completion. The point at which Substantial Completion has been achieved, all punch list items noted at Substantial Completion have been completed and all documents the Design-Builder Construction Manager is required to deliver to the Department as a condition to receiving final payment have been deliveredreceived by the Department.

Appears in 1 contract

Sources: Construction Management at Risk Agreement

Final Completion. The point at which Substantial Completion has been achieved, all punch list punchlist items noted at Substantial Completion have been completed and all documents the Design-Builder Contractor is required to deliver to the Department as a condition to receiving final payment have been delivered.

Appears in 1 contract

Sources: Construction Management at Risk Services Agreement

Final Completion. The point at which Substantial Completion has been achieved, all punch list punchlist items noted at Substantial Completion have been completed and all Project documents the Design-Builder is required to deliver to the Department as a condition to receiving receive final payment have been delivered.

Appears in 1 contract

Sources: Design Build Agreement