Final Notice of Acceptability of the Work. ENGINEER shall conduct a final inspection to determine if the completed work of Contractor is acceptable so that ENGINEER may recommend, in writing, final payment to Contractor. Accompanying the recommendation for final payment, ENGINEER shall indicate that the work is acceptable (subject to the Applications for Payment paragraphs) to the best of ENGINEER's knowledge, information and belief and based on the extent of the services performed and furnished by ENGINEER under this Agreement. ENGINEER shall not be responsible for the acts or omissions of any Contractor, or of any subcontractor, any supplier, or of any other person or organization performing or furnishing any of the work. ENGINEER shall not be responsible for Contractor's failure to perform or furnish the work in accordance with the Contract Documents.