Final Punchlist Clause Samples

The Final Punchlist clause outlines the process for identifying and addressing any remaining minor deficiencies or incomplete work at the end of a construction project. Typically, the contractor and owner conduct a walkthrough to compile a list of items that do not meet contract specifications, such as touch-up painting or minor repairs, which must be completed before final acceptance. This clause ensures that all outstanding issues are documented and resolved, providing a clear path to project completion and helping to prevent disputes over unfinished work.
Final Punchlist. The Punchlist complied by the Design Professional at the Inspection for Material Completion which lists all Minor Items and Permitted Incomplete Work.
Final Punchlist. Design Professional shall complete the creation of the Final Punchlist within five (5) days after the execution of the Certificate of Material Completion.
Final Punchlist. The Punchlist compiled by the Design Professional pursuant to Section 3.2.1.4 at the Inspection for Material Completion which lists all Minor Items and Permitted Incomplete Work. Guaranteed Maximum Price (GMP). The maximum amount that Owner is obligated to pay CM/GC for construction of the Project pursuant to the GMP Change Order.

Related to Final Punchlist