Common use of Float Time Clause in Contracts

Float Time. Float or slack is the amount of time between the early start date and the late start date, or the early finish date and the late finish date, of any of the activities in the schedule. All float time contained in the Work shall be shared between the District and DBE, but its use shall be determined by the District. Under no circumstances shall DBE be entitled to maintain a claim against the District for DBE’s failure to achieve either Substantial Completion or Final Completion on a date earlier than that set forth on said Project Milestone Schedule as the same may be adjusted by approved Change Orders.

Appears in 2 contracts

Sources: Design Build Agreement, Design Build Agreement