Common use of Format for Proposed Change Order Clause in Contracts

Format for Proposed Change Order. 17.5.1 The following format shall be used as applicable by the District and Developer (e.g. Change Orders, PCOs) to communicate proposed additions and/or deductions to the Contract, supported by attached documentation. Any spaces left blank will be deemed no change to cost or time.

Appears in 5 contracts

Sources: General Construction Agreement, General Construction Agreement, General Construction Agreement

Format for Proposed Change Order. 17.5.1 17.6.1 The following format shall be used as applicable by the District and Developer (e.g. Change Orders, PCOs) to communicate proposed additions and/or deductions to the Contract, supported by attached documentation. Any spaces left blank will be deemed no change to cost or time.

Appears in 2 contracts

Sources: General Construction Agreement, General Construction Agreement

Format for Proposed Change Order. 17.5.1 The 1The following format shall be used as applicable by the District and Developer (e.g. Change Orders, PCOs) to communicate proposed additions and/or deductions to the Contract, supported by attached documentation. Any spaces left blank will be deemed no change to cost or time.. WORK PERFORMED OTHER THAN BY DEVELOPER ADD DEDUCT

Appears in 1 contract

Sources: General Construction Agreement

Format for Proposed Change Order. 17.5.1 The following format shall be used as applicable by the District and Developer (e.g. Change Orders, PCOs) to communicate proposed additions and/or deductions to the Contract, supported by attached documentation. Any spaces left blank will be deemed no change to cost or time.. WORK PERFORMED

Appears in 1 contract

Sources: General Construction Agreement