Generator Interconnection Procedures. Bonneville shall adopt new tariff language as reflected in the Settlement Tariff, Attachment 2, to: a. Implement the following reforms pursuant to the Federal Energy Regulatory Commission’s (“Commission”) Order No. 845: The Interconnection Customer’s Option to Build, Dispute Resolution, Identification and Definition of Contingent Facilities, Transparency Regarding Study Models and Assumptions, Definition of Generating Facility in the Standard Large Generator Interconnection Procedures (“LGIP”) and Standard Large Generator Interconnection Agreement (“LGIA”), Interconnection Study Deadlines, Requesting Interconnection Service Below Generating Facility Capacity, Provisional Interconnection Service. b. Delete from Attachment L and N all tariff language that makes reference to Bonneville filing its tariff with the Commission; delete from Attachment L all tariff language that makes reference to filing an unexecuted LGIA with the Commission. By October 1, 2019, Bonneville shall develop a Business Practice that takes a phased approach to the implementation of the Commission’s Order No. 845 reform: Utilization of Surplus Interconnection Service and shall also revise the Large and Small Generator Interconnection Business Practices to clarify its process for determining whether an Interconnection Customer’s request for a modification constitutes a Material Modification.
Appears in 4 contracts
Sources: Settlement Agreement, Settlement Agreement, Settlement Agreement
Generator Interconnection Procedures. Bonneville shall adopt new tariff language as reflected in the Settlement Tariff, Attachment 2, to:
a. Implement the following reforms pursuant to the Federal Energy Regulatory Commission’s (“Commission”) Order No. 845: The Interconnection Customer’s Option to Build, Dispute Resolution, Identification and Definition of Contingent Facilities, Transparency Regarding Study Models and Assumptions, Definition of Generating Facility in the Standard Large Generator Interconnection Procedures (“LGIP”) and Standard Large Generator Interconnection Agreement (“LGIA”), Interconnection Study Deadlines, Requesting Interconnection Service Below Generating Facility Capacity, Provisional Interconnection Service.
b. Delete from Attachment L and N all tariff language that makes reference to Bonneville filing its tariff with the Commission; delete from Attachment L all tariff language that makes reference to filing an unexecuted LGIA with the Commission. By October 1, 2019, Bonneville ▇▇▇▇▇▇▇▇▇▇ shall develop a Business Practice that takes a phased approach to the implementation of the Commission’s Order No. 845 reform: Utilization of Surplus Interconnection Service and shall also revise the Large and Small Generator Interconnection Business Practices to clarify its process for determining whether an Interconnection Customer’s request for a modification constitutes a Material Modification.
Appears in 2 contracts
Sources: Settlement Agreement, Settlement Agreement