GMP Proposal. Design-Builder shall submit a GMP Proposal to the District, which shall include the following to establish the GMP, unless the parties mutually agree otherwise: 4.3.1.1 A proposed GMP, which shall be the sum of: 4.3.1.1.1 Design-Builder’s Fee of ($ .00); 4.3.1.1.2 The estimated Cost of the Work, inclusive of any General Allowance, if applicable; 4.3.1.1.3 Specific Allowances, if any; 4.3.1.1.4 General Conditions Lump Sum Cost; and 4.3.1.1.5 Pre-Construction and Design Services Lump Sum Cost. 4.3.1.2 The Basis of Design Documents, which may include, by way of example, the District’s Project Criteria and other relevant Contract Documents, which are set forth in detail and are attached to the GMP Proposal; 4.3.1.3 A list of the assumptions and clarifications made by Design-Builder in the preparation of the GMP Proposal, which list is intended to supplement the information contained in the drawings and specifications and is specifically included as part of the Basis of Design Documents; 4.3.1.4 A detailed Primavera CPM project schedule showing the scheduled Substantial Completion and Final Completion dates upon which the proposed GMP is based. 4.3.1.5 If applicable, a list of Allowance Items, Allowance Values, and a statement of their basis; 4.3.1.6 If applicable, a schedule of alternate prices; 4.3.1.7 If applicable, a schedule of unit prices; 4.3.1.8 If applicable, a statement of additional services which may be performed, but which are not included in the GMP and which, if performed, shall be the basis for an increase in the GMP and/or Project schedule; 4.3.1.9 Submission of a detailed construction estimate providing sufficient detail to assess labor rates, equipment rental, and subcontracts as provided under the definition of Cost of Work. Back-up shall be provided to verify that competitive market quotes were received for all equipment and subcontracted work. 4.3.1.10 The time limit for acceptance of the GMP Proposal.
Appears in 1 contract
Sources: Design Build Agreement
GMP Proposal. If requested by Owner, Design-Builder shall submit a GMP Proposal to the District, Owner which shall include the following to establish the GMPfollowing, unless the parties mutually agree otherwise:
4.3.1.1 i. A proposed GMP, which shall be the sum of:
4.3.1.1.1 A) Design-Builder’s Fee of ($ .00)as defined in Section 6.2.1 hereof;
4.3.1.1.2 B) The estimated Cost of the WorkWork as defined in Section 6.3 hereof, inclusive of any General AllowanceDesign-Builder’s Contingency as defined in Section 6.6.1.2 hereof; and
C) If applicable, if applicable;
4.3.1.1.3 Specific Allowances, if any;
4.3.1.1.4 General Conditions Lump Sum Cost; and 4.3.1.1.5 Pre-Construction and Design Services Lump Sum Costany prices established under Section 6.1.2 hereof.
4.3.1.2 ii. The Basis of Design Documents, which may include, by way of example, the DistrictOwner’s Project Criteria and other relevant Contract DocumentsCriteria, which are set forth in detail and are attached to the GMP Proposal;
4.3.1.3 iii. A list of the assumptions and clarifications made by Design-Builder in the preparation of the GMP Proposal, which list is intended to supplement the information contained in the drawings and specifications and is specifically included as part of the Basis of Design Documents;
4.3.1.4 A detailed Primavera CPM project schedule showing the scheduled iv. The Scheduled Substantial Completion and Final Completion dates Date upon which the proposed GMP is based., to the extent said date has not already been established under Section 5.2.1 hereof, and a schedule upon which the Scheduled Substantial Completion Date is based;
4.3.1.5 v. If applicable, a list of Allowance Items, Allowance Values, and a statement of their basis;
4.3.1.6 vi. If applicable, a schedule of alternate prices;
4.3.1.7 vii. If applicable, a schedule of unit prices;
4.3.1.8 viii. If applicable, a statement of additional services Additional Services which may be performed, performed but which are not included in the GMP and which, if performed, shall be the basis for an increase in the GMP and/or Project schedule;Contract Time(s); and
4.3.1.9 Submission of a detailed construction estimate providing sufficient detail to assess labor rates, equipment rental, and subcontracts as provided under the definition of Cost of Workix. Back-up shall be provided to verify that competitive market quotes were received for all equipment and subcontracted work.
4.3.1.10 The time limit for acceptance of the GMP Proposal.
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Design Builder
GMP Proposal. If requested by Owner, Design-Builder shall submit a GMP Proposal to the District, Owner which shall include the following to establish the GMPfollowing, unless the parties mutually agree otherwise:
4.3.1.1 6.6.2.1.1 A proposed GMP, which shall be the sum of:
4.3.1.1.1 i. Design-Builder’s Fee of ($ .00)as defined in Section 6.2.1 hereof;
4.3.1.1.2 ii. The estimated Cost of the WorkWork as defined in Section 6.3 hereof, inclusive of any General AllowanceDesign-Builder’s Contingency as defined in Section 6.6.1.2 hereof; and
iii. If applicable, if applicable;
4.3.1.1.3 Specific Allowances, if any;
4.3.1.1.4 General Conditions Lump Sum Cost; and 4.3.1.1.5 Pre-Construction and Design Services Lump Sum Costany prices established under Section 6.1.2 hereof.
4.3.1.2 6.6.2.1.2 The Basis of Design Documents, which may include, by way of example, the DistrictOwner’s Project Criteria and other relevant Contract DocumentsCriteria, which are set forth in detail and are attached to the GMP Proposal;
4.3.1.3 6.6.2.1.3 A list of the assumptions and clarifications made by Design-Builder in the preparation of the GMP Proposal, which list is intended to supplement the information contained in the drawings and specifications and is specifically included as part of the Basis of Design Documents;
4.3.1.4 A detailed Primavera CPM project schedule showing the scheduled 6.6.2.1.4 The Scheduled Substantial Completion and Final Completion dates Date upon which the proposed GMP is based., to the extent said date has not already been established under Section 5.2.1 hereof, and a schedule upon which the Scheduled Substantial Completion Date is based;
4.3.1.5 6.6.2.1.5 If applicable, a list of Allowance Items, Allowance Values, and a statement of their basis;
4.3.1.6 6.6.2.1.6 If applicable, a schedule of alternate prices;
4.3.1.7 6.6.2.1.7 If applicable, a schedule of unit prices;
4.3.1.8 6.6.2.1.8 If applicable, a statement of additional services Additional Services which may be performed, performed but which are not included in the GMP and which, if performed, shall be the basis for an increase in the GMP and/or Project schedule;Contract Time(s); and
4.3.1.9 Submission of a detailed construction estimate providing sufficient detail to assess labor rates, equipment rental, and subcontracts as provided under the definition of Cost of Work. Back-up shall be provided to verify that competitive market quotes were received for all equipment and subcontracted work.
4.3.1.10 6.6.2.1.9 The time limit for acceptance of the GMP Proposal.
Appears in 1 contract