Common use of Grounds for Extension Clause in Contracts

Grounds for Extension. If such application is made, the Contractor shall be entitled to an extension of time for delay in completion of the Work caused solely: 13.3.1 By the acts or omissions of the City, its officials, agents or employees; or 13.3.2 By the act or omissions of Other Contractors on this Project; or 13.3.3 By supervening conditions entirely beyond the control of either party hereto (such as, but not limited to, acts of God or the public enemy, excessive inclement weather, war or other national emergency making performance temporarily impossible or illegal, or strikes or labor disputes not brought about by any act or omission of the Contractor). 13.3.4 The Contractor shall, however, be entitled to an extension of time for such causes only for the number of Days of delay which the ACCO or the Board may determine to be due solely to such causes, and then only if the Contractor shall have strictly complied with all of the requirements of Articles 9 and 10.

Appears in 12 contracts

Sources: Construction Contract, Standard Construction Contract, Proposal for Bids

Grounds for Extension. If such application is made, the Contractor shall be entitled to an extension of time for delay in completion of the Work caused solely: 13.3.1 13.3.1. By the acts or omissions of the City, its officials, agents or employees; or 13.3.2 13.3.2. By the act or omissions of Other Contractors on this Project; or 13.3.3 13.3.3. By supervening conditions entirely beyond the control of either party hereto (such as, but not limited to, acts of God or the public enemy, excessive inclement weather, war or other national emergency making performance temporarily impossible or illegal, or strikes or labor disputes not brought about by any act or omission of the Contractor). 13.3.4 13.3.4. The Contractor shall, however, be entitled to an extension of time for such causes only for the number of Days of delay which the ACCO or the Board may determine to be due solely to such causes, and then only if the Contractor shall have strictly complied with all of the requirements of Articles 9 and 10.

Appears in 9 contracts

Sources: Construction Contract, Construction Contract, Supply and Service Agreement

Grounds for Extension. If such application is made, the Contractor shall be entitled to an extension of time for delay in completion of the Work caused solely: 13.3.1 46.3.1. By the acts or omissions of the City, its officials, agents or employees; or 13.3.2 46.3.2. By the act or omissions of Other Contractors on this Project; or 13.3.3 46.3.3. By supervening conditions entirely beyond the control of either party hereto (such as, but not limited to, acts of God or the public enemy, excessive inclement weather, war or other national emergency making performance temporarily impossible or illegal, or strikes or labor disputes not brought about by any act or omission of the Contractor). 13.3.4 46.3.4. The Contractor shall, however, be entitled to an extension of time for such causes only for the number of Days of delay which the ACCO or the Board may determine to be due solely to such causes, and then only if the Contractor shall have strictly complied with all of the requirements of Articles 9 and 10the Contract.

Appears in 8 contracts

Sources: Supply and Service Agreement, Furnish and Install Agreement, Furnish and Install Agreement

Grounds for Extension. If such application is made, the Contractor shall be entitled to an extension of time for delay in completion of the Work caused solely: 13.3.1 46.3.1. By the acts or omissions of the City, its officials, agents or employees; or 13.3.2 46.3.2. By the act or omissions of Other Contractors on this Project; or 13.3.3 46.3.3. By supervening conditions entirely beyond the control of either party hereto (such as, but not limited to, acts of God or the public enemy, excessive inclement weather, war or other national emergency making performance temporarily impossible or illegal, or strikes or labor disputes not brought about by any act or omission of the Contractor). 13.3.4 46.3.4. The Contractor shall, however, be entitled to an extension of time for such causes only for the number of Days of delay which the ACCO or the Board may determine to be due solely to such causes, and then only if the Contractor shall have strictly complied with all of the requirements of Articles 9 Article 42 and 10Article 43.

Appears in 5 contracts

Sources: Furnish and Install Agreement, Furnish and Install Agreement, Furnish and Install Agreement

Grounds for Extension. If such application is made, the Contractor shall be entitled to an extension of time for delay in completion of the Work caused solely: 13.3.1 By the acts or omissions of the City, its officials, agents or employees; or 13.3.2 By the act or omissions of Other Contractors on this Project; or 13.3.3 By supervening conditions entirely beyond the control of either party hereto (such as, but not limited to, acts of God or the public enemy, excessive inclement weather, war or other national emergency making performance temporarily impossible or illegal, or strikes or labor disputes not brought about by any act or omission of the Contractor). 13.3.4 13.1.4 The Contractor shall, however, be entitled to an extension of time for such causes only for the number of Days of delay which the ACCO or the Board may determine to be due solely to such causes, and then only if the Contractor shall have strictly complied with all of the requirements of Articles 9 and 10.

Appears in 2 contracts

Sources: Autoclave Sterilizer Maintenance and Repair Agreement, Agreement for Boilers, Heaters, Repairs and Maintenance Services