INDIVIDUAL PROJECT REQUIREMENTS. 3.3.1 Each IPPA shall represent a separate and distinct construction project(“Individual Project”). Attached to each IPPA and made a part of this Agreement is the Design, Construction and Equipment Budget, a component of which is the Individual Project Construction Budget. The Individual Project Construction Budget shall be defined as the total cost of constructing the Individual Project identified in the IPPA. A component of the Individual Project Construction Budget is the Construction Contract Award Price, hereinafter referred to as CCAP. The Engineer shall prepare drawings, specifications and other documents necessary so that the construction contract bid from a responsive, responsible bidding contractor, acceptable to the Owner, will be within the CCAP. 3.3.1.1 During the Design Phase of each Individual Project the Engineer shall prepare such estimates as it deems necessary, at no additional cost to the Owner, to assure itself that the estimated Individual Project cost is within the CCAP and shall supply such data, information or estimates as the Owner may require to substantiate the Engineer's contention that the Individual Project cost is within the CCAP. 3.3.1.2 With each Design Phase submittal of the Engineer to the Owner, the Engineer shall make the following statement in writing: "The drawings, specifications, and other documents submitted herewith, in my/our professional opinion, fulfill the Program of Requirements. Further, in my/our professional opinion, the above mentioned documents submitted herewith have been prepared in accordance with the Engineering Services Agreement." With each Design Phase submittal of the Engineer to the Owner and with his certification of the Final Payment to the contractor, the Engineer shall make the following statement in writing: "No asbestos containing building materials have been specified and to the best of my/our knowledge and belief none have been incorporated into this Project."
Appears in 10 contracts
Sources: Master Mechanical Engineering Services Agreement, Master Civil Engineering Services Agreement, Master Civil Engineering Services Agreement
INDIVIDUAL PROJECT REQUIREMENTS. 3.3.1 Each IPPA shall represent a separate and distinct construction project(“Individual Project”). Attached to each IPPA and made a part of this Agreement is the Design, Construction and Equipment Budget, a component of which is the Individual Project Construction Budget. The Individual Project Construction Budget shall be defined as the total cost of constructing the Individual Project project identified in the IPPA. A component of the Individual Project Construction Budget is the Construction Contract Award Price, hereinafter referred to as CCAP. The Engineer Design Consultant shall prepare drawings, specifications and other documents necessary so that the construction contract bid from a responsive, responsible bidding contractor, acceptable to the Owner, will be within the CCAP.
3.3.1.1 During the Design Phase of each Individual Project the Engineer Design Consultant shall prepare such estimates as it deems necessary, at no additional cost to the Owner, to assure itself that the estimated Individual Project cost is within the CCAP and shall supply such data, information or estimates as the Owner may require to substantiate the EngineerDesign Consultant's contention that the Individual Project cost is within the CCAP.
3.3.1.2 With each Design Phase submittal of the Engineer Design Consultant to the Owner, the Engineer Design Consultant shall make the following statement in writing: "The drawings, specifications, and other documents submitted herewith, in my/our professional opinion, fulfill the Program of Requirements. Further, in my/our professional opinion, the above mentioned documents submitted herewith have been prepared in accordance with the Engineering Design Consultant Services Agreement." With each Design Phase submittal of the Engineer Design Consultant to the Owner and with his certification of the Final Payment to the contractor, the Engineer Design Consultant shall make the following statement in writing: "No asbestos containing building materials have been specified and to the best of my/our knowledge and belief none have been incorporated into this Project."
Appears in 6 contracts
Sources: Master Mobile Classroom Design Consultant Services Agreement, Master Design Consultant Services Agreement, Design Consultant Services Agreement
INDIVIDUAL PROJECT REQUIREMENTS. 3.3.1 Each IPPA shall represent a separate and distinct construction project(“Individual Project”). Attached to each IPPA and made a part of this Agreement is the Design, Construction and Equipment Budget, a component of which is the Individual Project Construction Budget. The Individual Project Construction Budget shall be defined as the total cost of constructing the Individual Project project identified in the IPPA. A component of the Individual Project Construction Budget is the Construction Contract Award Price, hereinafter referred to as CCAP. The Engineer Landscape Architect shall prepare drawings, specifications and other documents necessary so that the construction contract bid from a responsive, responsible bidding contractor, acceptable to the Owner, will be within the CCAP.
3.3.1.1 During the Design Phase of each Individual Project the Engineer Landscape Architect shall prepare such estimates as it deems necessary, at no additional cost to the Owner, to assure itself that the estimated Individual Project cost is within the CCAP and shall supply such data, information or estimates as the Owner may require to substantiate the EngineerLandscape Architect's contention that the Individual Project cost is within the CCAP.
3.3.1.2 With each Design Phase submittal of the Engineer Landscape Architect to the Owner, the Engineer Landscape Architect shall make the following statement in writing: "The drawings, specifications, and other documents submitted herewith, in my/our professional opinion, fulfill the Program of Requirements. Further, in my/our professional opinion, the above mentioned documents submitted herewith have been prepared in accordance with the Engineering Landscape Architect Services Agreement." With each Design Phase submittal of the Engineer Landscape Architect to the Owner and with his certification of the Final Payment to the contractor, the Engineer Landscape Architect shall make the following statement in writing: "No asbestos containing building materials have been specified and to the best of my/our knowledge and belief none have been incorporated into this Project."
Appears in 2 contracts
Sources: Master Landscape Architect Services Agreement, Master Landscape Architect Services Agreement
INDIVIDUAL PROJECT REQUIREMENTS. 3.3.1 Each IPPA shall represent a separate and distinct construction project(“Individual Project”). Attached to each IPPA and made a part of this Agreement is the Design, Construction and Equipment Budget, a component of which is the Individual Project Construction Budget. The Individual Project Construction Budget shall be defined as the total cost of constructing the Individual Project identified in the IPPA. A component of the Individual Project Construction Budget is the Construction Contract Award Price, hereinafter referred to as CCAP. The Engineer shall prepare drawings, specifications and other documents necessary so that the construction contract bid from a responsive, responsible bidding contractor, acceptable to the Owner, will be within the CCAP.
3.3.1.1 During the Design Phase of each Individual Project the Engineer shall prepare such estimates as it deems necessary, at no additional cost to the Owner, to assure itself that the estimated Individual Project cost is within the CCAP and shall supply such data, information or estimates as the Owner may require to substantiate the Engineer's contention that the Individual Project cost is within the CCAP.
3.3.1.2 With each Design Phase submittal of the Engineer to the Owner, the Engineer shall make the following statement in writing: "The drawings, specifications, and other documents submitted herewith, in my/our professional opinion, fulfill the Program of Requirements. Further, in my/our professional opinion, the above mentioned documents submitted herewith have been prepared in accordance with the Engineering Services Agreement." With each Design Phase submittal of the Engineer to the Owner and with his certification of the Final Payment to the contractor, the Engineer shall make the following statement in writing: "No asbestos asbestos-containing building materials have been specified and to the best of my/our knowledge and belief none have been incorporated into this Project."
Appears in 2 contracts
Sources: Master Civil Engineering Services Agreement, Master Traffic Engineering Services Agreement
INDIVIDUAL PROJECT REQUIREMENTS. 3.3.1 Each IPPA shall represent a separate and distinct construction project(“Individual project (“Individual Project”). Attached to each IPPA and made a part of this Agreement is the Design, Construction and Equipment Budget, a component of which is the Individual Project Construction Budget. The Individual Project Construction Budget shall be defined as the total cost of constructing the Individual Project project identified in the IPPA. A component of the Individual Project Construction Budget is the Construction Contract Award Price, hereinafter referred to as CCAP. The Engineer Design Consultant shall prepare drawings, specifications and other documents necessary so that the construction contract bid from a responsive, responsible bidding contractor, acceptable to the Owner, will be within the CCAP.
3.3.1.1 During the Design Phase of each Individual Project the Engineer Design Consultant shall prepare such estimates as it deems necessary, at no additional cost to the Owner, to assure itself that the estimated Individual Project cost is within the CCAP and shall supply such data, information or estimates as the Owner may require to substantiate the EngineerDesign Consultant's contention that the Individual Project cost is within the CCAP.
3.3.1.2 With each Design Phase submittal of the Engineer Design Consultant to the Owner, the Engineer Design Consultant shall make the following statement in writing: "The drawings, specifications, and other documents submitted herewith, in my/our professional opinion, fulfill the Program of Requirements. Further, in my/our professional opinion, the above mentioned documents submitted herewith have been prepared in accordance with the Engineering Design Consultant Services Agreement." With each Design Phase submittal of the Engineer Design Consultant to the Owner and with his certification of the Final Payment to the contractor, the Engineer Design Consultant shall make the following statement in writing: "No asbestos containing building materials have been specified and to the best of my/our knowledge and belief none have been incorporated into this Project."
Appears in 1 contract
INDIVIDUAL PROJECT REQUIREMENTS. 3.3.1 Each IPPA shall represent a separate and distinct construction project(“Individual Project”). Attached to each IPPA and made a part of this Agreement is the Design, Construction and Equipment Budget, a component of which is the Individual Project Construction Budget. The Individual Project Construction Budget shall be defined as the total cost of constructing the Individual Project project identified in the IPPA. A component of the Individual Project Construction Budget is the Construction Contract Award Price, hereinafter referred to as CCAP. The Engineer Landscape Architect shall prepare drawings, specifications and other documents necessary so that the construction contract bid from a responsive, responsible bidding contractor, acceptable to the Owner, will be within the CCAP.
3.3.1.1 3.3.2 During the Design Phase of each Individual Project the Engineer Landscape Architect shall prepare such estimates as it deems necessary, at no additional cost to the Owner, to assure itself that the estimated Individual Project cost is within the CCAP and shall supply such data, information or estimates as the Owner may require to substantiate the EngineerLandscape Architect's contention that the Individual Project cost is within the CCAP.
3.3.1.2 3.3.3 With each Design Phase submittal of the Engineer Landscape Architect to the Owner, the Engineer Landscape Architect shall make the following statement in writing: "The drawings, specifications, and other documents submitted herewith, in my/our professional opinion, fulfill the Program of Requirements. Further, in my/our professional opinion, the above mentioned documents submitted herewith have been prepared in accordance with the Engineering Landscape Architect Services Agreement." With each Design Phase submittal of the Engineer Landscape Architect to the Owner and with his certification of the Final Payment to the contractor, the Engineer Landscape Architect shall make the following statement in writing: "No asbestos containing building materials have been specified and to the best of my/our knowledge and belief none have been incorporated into this Project."
Appears in 1 contract
INDIVIDUAL PROJECT REQUIREMENTS. 3.3.1 Each IPPA shall represent a separate and distinct construction project(“Individual Project”). Attached to each IPPA and made a part of this Agreement is the Design, Construction and Equipment Budget, a component of which is the Individual Project Construction Budget. The Individual Project Construction Budget shall be defined as the total cost of constructing the Individual Project project identified in the IPPA. A component of the Individual Project Construction Budget is the Construction Contract Award Price, hereinafter referred to as CCAP. The Engineer Landscape Architect shall prepare drawings, specifications and other documents necessary so that the construction contract bid from a responsive, responsible bidding contractor, acceptable to the Owner, will be within the CCAP.
3.3.1.1 During the Design Phase of each Individual Project the Engineer Landscape Architect shall prepare such estimates as it deems necessary, at no additional cost to the Owner, to assure itself that the estimated Individual Project cost is within the CCAP and shall supply such data, information or estimates as the Owner may require to substantiate the EngineerLandscape Architect's contention that the Individual Project cost is within the CCAP.
3.3.1.2 With each Design Phase submittal of the Engineer Landscape Architect to the Owner, the Engineer Landscape Architect shall make the following statement in writing: "The drawings, specifications, and other documents submitted herewith, in my/our professional opinion, fulfill the Program of Requirements. Further, in my/our professional opinion, the above mentioned documents submitted herewith have been prepared in accordance with the Engineering Landscape Architect Services Agreement." With each Design Phase submittal of the Engineer Landscape Architect to the Owner and with his certification of the Final Payment to the contractor, the Engineer Landscape Architect shall make the following statement in writing: "No asbestos asbestos-containing building materials have been specified and to the best of my/our knowledge and belief none have been incorporated into this Project."
Appears in 1 contract
INDIVIDUAL PROJECT REQUIREMENTS. 3.3.1 Each IPPA shall represent a separate and distinct construction project(“Individual Project”). Attached to each IPPA and made a part of this Agreement is the Design, Construction and Equipment Budget, a component of which is the Individual Project Construction Budget. The Individual Project Construction Budget shall be defined as the total cost of constructing the Individual Project project identified in the IPPA. A component of the Individual Project Construction Budget is the Construction Contract Award Price, hereinafter referred to as CCAP. The Engineer Roof and Building Envelope Consultant shall prepare drawings, specifications and other documents necessary so that the construction contract bid from a responsive, responsible bidding contractor, acceptable to the Owner, will be within the CCAP.
3.3.1.1 During the Design Phase of each Individual Project the Engineer Roof and Building Envelope Consultant shall prepare such estimates as it deems necessary, at no additional cost to the Owner, to assure itself that the estimated Individual Project cost is within the CCAP and shall supply such data, information or estimates as the Owner may require to substantiate the EngineerRoof and Building Envelope Consultant's contention that the Individual Project cost is within the CCAP.
3.3.1.2 With each Design Phase submittal of the Engineer Roof and Building Envelope Consultant to the Owner, the Engineer Roof and Building Envelope Consultant shall make the following statement in writing: "The drawings, specifications, and other documents submitted herewith, in my/our professional opinion, fulfill the Program of Requirements. Further, in my/our professional opinion, the above mentioned documents submitted herewith have been prepared in accordance with the Engineering Roof and Building Envelope Consultant Services Agreement." With each Design Phase submittal of the Engineer Roof and Building Envelope Consultant to the Owner and with his certification of the Final Payment to the contractor, the Engineer Roof and Building Envelope Consultant shall make the following statement in writing: "No asbestos containing building materials have been specified and to the best of my/our knowledge and belief none have been incorporated into this Project."
Appears in 1 contract
Sources: Master Roof and Building Envelope Consultant Services Agreement
INDIVIDUAL PROJECT REQUIREMENTS. 3.3.1 Each IPPA shall represent a separate and distinct construction project(“Individual Project”). Attached to each IPPA and made a part of this Agreement is the Design, Construction and Equipment Budget, a component of which is the Individual Project Construction Budget. The Individual Project Construction Budget shall be defined as the total cost of constructing the Individual Project project identified in the IPPA. A component of the Individual Project Construction Budget is the Construction Contract Award Price, hereinafter referred to as CCAP. The Engineer Roof and Building Envelope Consultant shall prepare drawings, specifications and other documents necessary so that the construction contract bid from a responsive, responsible bidding contractor, acceptable to the Owner, will be within the CCAP.
3.3.1.1 During the Design Phase of each Individual Project the Engineer Roof and Building Envelope Consultant shall prepare such estimates as it deems necessary, at no additional cost to the Owner, to assure itself that the estimated Individual Project cost is within the CCAP and shall supply such data, information or estimates as the Owner may require to substantiate the EngineerRoof and Building Envelope Consultant's contention that the Individual Project cost is within the CCAP.
3.3.1.2 With each Design Phase submittal of the Engineer Roof and Building Envelope Consultant to the Owner, the Engineer Roof and Building Envelope Consultant shall make the following statement in writing: "The drawings, specifications, and other documents submitted herewith, in my/our professional opinion, fulfill the Program of Requirements. Further, in my/our professional opinion, the above mentioned documents submitted herewith have been prepared in accordance with the Engineering Roof and Building Envelope Consultant Services Agreement." With each Design Phase submittal of the Engineer Roof and Building Envelope Consultant to the Owner and with his certification of the Final Payment to the contractor, the Engineer Roof and Building Envelope Consultant shall make the following statement in writing: "No asbestos asbestos-containing building materials have been specified and to the best of my/our knowledge and belief none have been incorporated into this Project."
Appears in 1 contract
Sources: Master Roof and Building Envelope Consultant Services Agreement
INDIVIDUAL PROJECT REQUIREMENTS. 3.3.1 Each IPPA shall represent a separate and distinct construction project(“Individual Project”). Attached to each IPPA and made a part of this Agreement is the Design, Construction and Equipment Budget, a component of which is the Individual Project Construction Budget. The Individual Project Construction Budget shall be defined as the total cost of constructing the Individual Project project identified in the IPPA. A component of the Individual Project Construction Budget is the Construction Contract Award Price, hereinafter referred to as CCAP. The Engineer Roof and Building Envelope Consultant shall prepare drawings, specifications and other documents necessary so that the construction contract bid from a responsive, responsible bidding contractor, acceptable to the Owner, will be within the CCAP.
3.3.1.1 3.3.2 During the Design Phase of each Individual Project the Engineer Roof and Building Envelope Consultant shall prepare such estimates as it deems necessary, at no additional cost to the Owner, to assure itself that the estimated Individual Project cost is within the CCAP and shall supply such data, information or estimates as the Owner may require to substantiate the EngineerRoof and Building Envelope Consultant's contention that the Individual Project cost is within the CCAP.
3.3.1.2 3.3.3 With each Design Phase submittal of the Engineer Roof and Building Envelope Consultant to the Owner, the Engineer Roof and Building Envelope Consultant shall make the following statement in writing: "The drawings, specifications, and other documents submitted herewith, in my/our professional opinion, fulfill the Program of Requirements. Further, in my/our professional opinion, the above mentioned documents submitted herewith have been prepared in accordance with the Engineering Roof and Building Envelope Consultant Services Agreement." With each Design Phase submittal of the Engineer Roof and Building Envelope Consultant to the Owner and with his certification of the Final Payment to the contractor, the Engineer Roof and Building Envelope Consultant shall make the following statement in writing: "No asbestos containing building materials have been specified and to the best of my/our knowledge and belief none have been incorporated into this Project."
Appears in 1 contract
Sources: Master Roof and Building Envelope Consultant Services Agreement