Initial Consultation. Upon issuance by VPRA of a Request for Change Proposal, VPRA and Design-Builder shall: (a) have a first consultation to define the proposed scope of the change no later than two (2) Working Days after Design-Builder receives a Request for Change Proposal; and (b) have a second consultation concerning the estimated cost and time impacts no later than seven (7) Working Days after the first consultation. Design-Builder shall provide data regarding the Request for Change Proposal as requested by VPRA.
Appears in 2 contracts
Sources: Design Build Agreement, Design Build Agreement
Initial Consultation. Upon issuance by VPRA of a Request for Change Proposal, VPRA and Design-Builder Contractor shall:
(a) have a first consultation to define the proposed scope of the change no later than two (2) Working Days after Design-Builder Contractor receives a Request for Change Proposal; and
(b) have a second consultation concerning the estimated cost and time impacts no later than seven (7) Working Days after the first consultation. Design-Builder Contractor shall provide data regarding the Request for Change Proposal as requested by VPRA.
Appears in 1 contract
Sources: Construction Manager / General Contractor Agreement