Interconnections. Contractor shall provide the following interconnections. Points will be located as shown on the Site Interconnection Drawing in Exhibit B, Attachment I. Contractor shall be responsible for coordinating interconnection design and construction as required for proper tie-in suitable to Owner and affected parties. The Contractor is responsible for determining actual distances required. o Natural Gas - Provide a tie-in to the Transco pipeline at the southern portion of the site.