Interference with Tests on Completion. If the Contractor suffers delay or is prevented, for more than 14 days, from carrying out the Tests on Completion by a cause for which the Employer is responsible and/or incurs Cost as a result of this delay in carrying out the Tests on Completion, the Contractor shall give notice to the Engineer and shall be entitled subject to clause 20 [Claims and Disputes] to: (a) an extension of time for any such delay, if completion is or will be delayed, under sub-clause 8.4 [Extension of Time for Completion]; and (b) payment of any such Cost plus Profit, which shall be included in the Contract Price. After receiving this notice, the Engineer shall proceed in accordance with sub-clause 3.5 [Determinations] to agree or determine these matters.
Appears in 13 contracts
Sources: Crane Supply Contract, Crane Supply Contract, Crane Supply Contract