Common use of Interference with Tests on Completion Clause in Contracts

Interference with Tests on Completion. If the Contractor is prevented, for more than 14 days, from carrying out the Tests on Completion by a cause for which the Employer is responsible, the Employer shall be deemed to have taken over the Works or Section (as the case may be) on the date when the Tests on Completion would otherwise have been completed. The Engineer shall then issue a Taking-Over Certificate accordingly, and the Contractor shall carry out the Tests on Completion as soon as practicable, before the expiry date of the Defects Notification Period. The Engineer shall require the Test on Completion to be carried out by giving 14 days’ notice and in accordance with the relevant provisions of the Contract. If the Contractor suffers delay and /or incurs Cost as a result of this delay in carrying out the Tests on Completion, the Contractor shall give notice to the Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to: an extension of time for any such delay, if completion is our will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], and payment of any such Cost plus reasonable profit, which shall be included in the Contract Price. After receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine these matters.

Appears in 1 contract

Sources: Contract Agreement

Interference with Tests on Completion. If the Contractor is prevented, for more than 14 (Fourteen) days, from carrying out the Tests on Completion by a cause for which the Employer is Employer/s is/are responsible, the Employer shall be deemed to have taken over the Works or Section (as the case may be) on the date when the Tests on Completion would otherwise have been completed. The Engineer shall then issue a Taking-Over Certificate accordingly, and the Contractor shall carry out the Tests on Completion as soon as practicable, before the expiry date of the Defects Notification Period. The Engineer shall require the Test on Completion to be carried out by giving 14 days’ notice and in accordance with the relevant provisions of the Contract. If the Contractor suffers delay and /or and/or incurs Cost as a result of this delay in carrying out the Tests on Completion, the Contractor shall give notice to the Engineer Employer/s and the financial institution providing the funding for the Project/s and shall be entitled entitled, subject to Sub-Clause 20.1 Clause 25.1 [Contractor’s 's Claims] to: : (a) an extension of time for any such delay, if completion is our or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], and and (b) payment of any such Cost Cost-plus reasonable profit, which shall be included in added to the Contract Price. , upon notice to the financial institution providing the funding for the Project/s. After receiving this notice, the Engineer Employer/s shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine these matters.

Appears in 1 contract

Sources: Public Private Partnership Agreement

Interference with Tests on Completion. If the Contractor is prevented, for more than 14 days, from carrying out the Tests on Completion by a cause for which the Employer is responsible, the Employer shall be deemed to have taken over the Works or Section (as the case may be) on the date when the Tests on Completion would otherwise have been completed. The Engineer shall then issue a Taking-Over Certificate accordingly, and the Contractor shall carry out the Tests on Completion as soon as practicable, before the expiry date of the Defects Notification Period. The Engineer shall require the Test Tests on Completion to be carried out by giving 14 days’ notice and in accordance with the relevant provisions of the Contract. If the Contractor suffers delay and /or and/or incurs Cost as a result of this delay in carrying out the Tests on Completion, the Contractor shall give notice to the Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to: : (a) an extension of time for any such delay, if completion is our or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], and and (b) payment of any such Cost plus reasonable profit, which shall be included in the Contract Price. After receiving this notice, the Engineer shall proceed in accordance with Sub-Sub- Clause 3.5 [Determinations] to agree or determine these matters.

Appears in 1 contract

Sources: Unit Price Contract

Interference with Tests on Completion. If the Contractor is prevented, for more than 14 days, from carrying out the Tests on Completion by a cause for which the Employer is responsible, the Employer shall be deemed to have taken over the Works or Section (as the case may be) on the date when the Tests on Completion would otherwise have been completed. The Engineer shall then issue a Taking-Over Certificate accordingly, and the Contractor shall carry out the Tests on Completion as soon as practicable, before the expiry date of the Defects Notification Period. The Engineer shall require the Test Tests on Completion to be carried out by giving 14 days’ notice and in accordance with the relevant provisions of the Contract. If the Contractor suffers delay and /or and/or incurs Cost as a result of this delay in carrying out the Tests on Completion, the Contractor shall give notice to the Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to: : (a) an extension of time for any such delay, if completion is our or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], and SAMPLE (b) payment of any such Cost plus reasonable profit, which shall be included in the Contract Price. After receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine these matters.

Appears in 1 contract

Sources: Contract Agreement