Common use of Interference with Tests on Completion Clause in Contracts

Interference with Tests on Completion. If the Contractor suffers delay or is prevented, for more than 14 days, from carrying out the Tests on Completion by a cause for which the Employer is responsible and/or incurs Cost as a result of this delay in carrying out the Tests on Completion, the Contractor shall give notice to the Engineer and shall be entitled subject to clause 20 [Claims, Disputes and Arbitration] to:

Appears in 2 contracts

Sources: Contractor Agreement, Contractor Agreement