Issue of Completion Notice. If the Developer considers that the Works are Complete it must serve a notice on Council within 14 days of Completion which: i. is in writing; and ii. specifies the date on which the Developer believes the Works were Completed.
Appears in 1 contract
Sources: Planning Agreement
Issue of Completion Notice. If the Developer considers that the Works are an Item of Work is Complete it must serve a notice on Council within 14 fourteen (14) days of Completion of that item which:
i. is in writing; and
ii. specifies the date on which the Developer believes the Works were Completed.
Appears in 1 contract
Sources: Voluntary Planning Agreement