IUK Daily Delivery Report. (a) IUK will notify National Grid Gas of the end of day delivered quantities as set out in Schedule B. IUK will provide the notice not later than 08:00 hours on each Gas Day D+1. The notice will specify the total quantity and the average GCV in MJ/NM3 of the Natural Gas offtaken at the Interconnection Point by the IUK Shippers (deemed during Reverse Flow) and the total quantity of Natural Gas delivered at the Interconnection Point by IUK Shippers (deemed during Forward Flow) during the previous Gas Day. D. (b) IUK shall issue a revised IUK Daily Delivery Report if the GCV or any quantity delivered or offtaken has changed from the previous notification. A revision to an IUK Daily Delivery Report should be considered exceptional (e.g. for correction of transmission errors) and shall only be issued before Gas Day D+5.