Limitation on Project Co’s Remedies. To the extent Project Co has claimed for relief or compensation for a Supervening Event, pursuant to Section 8 [Supervening Events], Project Co may not make any further claim against the Authority for costs, losses, damages or expenses incurred by Project Co, or for any other relief, in respect of any such events provided that nothing in this Section 9.7 [Limitation on Project Co's Remedies] will limit Project Co’s right to: (a) deliver to the Authority a Dispute Notice or a notice of default or termination pursuant to Section 13 [Authority Events of Default] and pursue all remedies in respect thereof; or (b) pursue any other express remedy available to Project Co under this Agreement or any equitable remedy, including injunctive relief and specific performance.
Appears in 1 contract
Sources: Project Agreement
Limitation on Project Co’s Remedies. To the extent Project Co has claimed or is entitled to claim for relief or compensation for a Supervening Event, pursuant to Section 8 [(Supervening Events]), Project Co may not make any further claim against the Authority for costs, losses, damages or expenses incurred by Project Co, or for any other relief, in respect of any such events provided that nothing in this Section 9.7 [(Limitation on Project Co's ’s Remedies] ) will limit Project Co’s right to:
(a) deliver to the Authority a Dispute Notice or a notice of default or termination pursuant to Section 13 [(Authority Events of Default] ) and pursue all remedies in respect thereof; or
(b) pursue any other express remedy available to Project Co under this Agreement or any equitable remedy, including injunctive relief and specific performance.performance.
Appears in 1 contract
Sources: Project Agreement
Limitation on Project Co’s Remedies. To the extent Project Co has claimed or is entitled to claim for relief or compensation for a Supervening Event, pursuant to Section 8 [Supervening Events], Project Co may not make any further claim against the Authority Province for costs, losses, damages or expenses incurred by Project Co, or for any other relief, in respect of any such events provided that nothing in this Section 9.7 [Limitation on Project Co's Remedies] will limit Project Co’s right to:
(a) deliver to the Authority Province a Dispute Notice or a notice of default or termination pursuant to Section 13 [Authority Province Events of Default] and pursue all remedies in respect thereof; or
(b) pursue any other express remedy available to Project Co under this Agreement or any equitable remedy, including injunctive relief and specific performance.performance.
Appears in 1 contract
Sources: Project Agreement