Limitations on Liquidated Damages Clause Samples

POPULAR SAMPLE Copied 4 times
Limitations on Liquidated Damages. ‌ (a) The aggregate amount of liquidated damages payable by Seller as Reduction Amounts under Section 24.2 (“Critical Milestone Guarantee Liquidated Damages”) shall not exceed, in the aggregate, an amount equal to 5% of the Purchase Price. (b) The amount of liquidated damages payable by Seller for delays in achieving Substantial Completion under Section 24.3 (“Liquidated Damages for Delay in Substantial Completion”) shall not exceed, in the aggregate, an amount equal to 30% of the Purchase Price.
Limitations on Liquidated Damages. (a) The aggregate amount of liquidated damages payable by Contractor as Reduction Amounts under Section 23.2 shall not exceed, in the aggregate, an amount equal to 5% of the Contract Price set forth in Section 3.1(a). (b) The amount of liquidated damages payable by Contractor for delays in achieving Substantial Completion under Section 23.3 shall not exceed, in the aggregate, an amount equal to 30% of the Contract Price set forth in Section 3.1(a). (c) The amount of liquidated damages payable by Contractor attributable to failure to meet the Guaranteed Net Capacity pursuant to Section 23.4 shall not exceed, in the aggregate, an amount equal to 15% of the Contract Price. (d) The amount of liquidated damages payable by Contractor attributable to failure to meet the Guaranteed Net Heat Rate pursuant to Section 23.4 shall not exceed, in the aggregate, an amount equal to 20% of the Contract Price. (e) The amount of liquidated damages payable by Contractor attributable to failure to meet the startup and commissioning requirements pursuant to Section 23.5 shall not exceed, in the aggregate, an amount equal to 15% of the Contract Price. (f) The amount of liquidated damages under paragraphs (a) through (e) shall not exceed, in the aggregate, an amount equal to 50% of the Contract Price. (g) Without prejudice to or limitation of Contractor’s liabilities and obligations set forth under paragraphs (a) through (e), all of which shall be in excess of and not subject to the limitation contained in this paragraph (e), the aggregate liability of Contractor to Company shall not exceed one hundred percent (100%) of the amount of Contract Price.
Limitations on Liquidated Damages. Liquidated damages shall not exceed the total Contract Price. Liquidated damages shall not be assessed concurrently but the largest amount on each day shall be assessed.

Related to Limitations on Liquidated Damages

  • Limitations on Amounts A Letter of Credit shall be issued, amended, renewed or extended only if (and upon issuance, amendment, renewal or extension of each Letter of Credit the Borrower shall be deemed to represent and warrant that), after giving effect to such issuance, amendment, renewal or extension (i) the aggregate LC Exposure of the Issuing Bank (determined for these purposes without giving effect to the participations therein of the Lenders pursuant to paragraph (e) of this Section) shall not exceed $25,000,000, (ii) the total Multicurrency Credit Exposures shall not exceed the aggregate Multicurrency Commitment and (iii) the total Covered Debt Amount shall not exceed the Borrowing Base then in effect.

  • Limitations on Amount (a) ▇▇. ▇▇▇▇▇▇ and Seller will have no liability (for indemnification or otherwise) with respect to the matters described in clauses (a) and (b) of Section 9.02 until the total of all Damages with respect to such matters exceeds $100,000 and then only to the extent all such Damages exceed in the aggregate $100,000. Notwithstanding the foregoing, the aggregate liability of ▇▇. ▇▇▇▇▇▇ and Seller under this Article IX (other than Section 9.03) shall not exceed $1,500,000; provided, however that this limit will not apply to the representations and warranties in Sections 3.01, 3.02, and 3.13 or any fraudulent acts or omissions or intentional material misrepresentations on the part of ▇▇. ▇▇▇▇▇▇ or Seller. (b) Buyer shall not have any liability (for indemnification or otherwise) with respect to the matters described in clauses (a) and (b) of Section 9.04 until the total of all Damages with respect to such matters exceeds $100,000 and then only to the extent all such Damages exceed in the aggregate $100,000. Notwithstanding the foregoing, the aggregate liability of Buyer under Article IX shall not exceed $1,500,000, provided, however that this limit will not apply to the representations and warranties in Section 4.02 or any fraudulent acts or omissions or intentional material misrepresentations on the part of Buyer. (c) No indemnitor will have any liability (for indemnification or otherwise) for any Damages (i) for punitive, exemplary or special damages of any nature, (ii) for indirect or consequential damages, including damages for lost profit, lost business opportunity or damage to business reputation, or (iii) that, at the time written notice thereof is delivered to any indemnitor, are contingent, speculative or unquantified. (d) [Reserved] (e) [Reserved] (f) The amount of Damages for which the Buyer Indemnified Persons or Codina Indemnified Persons may be entitled to seek indemnification under this Agreement will be reduced by the amount of any insurance proceeds or other payment from a third party received or receivable by any Buyer Indemnified Person or Codina Indemnified Person, as applicable, with respect to such Damages and the amount of any deduction, credit or other Tax benefit that any Buyer Indemnified Person or Codina Indemnified Person is entitled to with respect to such Damages (taking into account the time at which such benefit is expected to be actually realized). If a Buyer Indemnified Person or Codina Indemnified Person, after having received any indemnification payment pursuant to this Agreement with respect to any Damages, subsequently receives any insurance proceeds or other payment or recognizes any deduction, credit or other Tax benefit with respect to such Damages, Buyer or ▇▇. ▇▇▇▇▇▇ and Seller, as the case may be, will promptly refund and pay to the Buyer Indemnified Persons or Codina Indemnified Persons, as the case may be, an amount equal to such insurance proceeds, payment or benefit. (g) Buyer will, and will use commercially reasonable efforts to cause each of the other Buyer Indemnified Persons to, use commercially reasonable efforts to mitigate any Damages with respect to which it may be entitled to seek indemnification pursuant to this Agreement. Buyer will, and will use commercially reasonable efforts to cause each of the other Buyer Indemnified Persons to, use commercially reasonable efforts to obtain all insurance proceeds or other payments from third parties, and all Tax refunds or other Tax benefits, that may be available with respect to any Damages with respect to which it may be entitled to indemnification under this Agreement. (h) If any indemnitor is indemnified for any Damages pursuant to this Agreement with respect to any claim by a third party, the indemnitor shall consider in good faith a request for subrogation on the part of the indemnitee.

  • Limitations on Damages Neither Party shall be liable for any consequential, special or indirect losses or damages suffered by the other Party, whether or not the likelihood of such losses or damages was known by the Party.

  • Payment of Liquidated Damages If you supply all or some of your milk to a third party during a Month you must, if required by DFMC, immediately pay to DFMC liquidated damages for that Month calculated as follows: $X = W cents x (Y – Z) Where: $X is the amount payable by you to DFMC for the relevant Month. If $X is a negative amount, no amount is payable by you. Y is the average monthly litres you have supplied to DFMC based on the 12 months immediately preceding the relevant Month (or in the event you have not supplied DFMC for 12 months, the average monthly litres you have supplied to DFMC during the period you have supplied DFMC). Z is the number of litres supplied to DFMC by you for the relevant Month.

  • Limitations on Payments (a) Anything in this Agreement to the contrary notwithstanding, in the event that it shall be determined as set forth herein that any payment or distribution by the Corporation or the Bank to or for the benefit of Executive, whether paid or payable or distributed or distributable pursuant to the terms of this Agreement or otherwise (a “Payment”), would constitute an “excess parachute payment” within the meaning of Section 280G of the Code, and that it would be economically advantageous to Executive to reduce the Payment to avoid or reduce the taxation of excess parachute payments under Section 4999 of the Code, the aggregate present value of amounts payable or distributable to or for the benefit of Executive pursuant to this Agreement (such payments or distributions pursuant to this Agreement are hereinafter referred to as “Agreement Payments”) shall be reduced (but not below zero) to the Reduced Amount. The “Reduced Amount” shall be an amount expressed in present value which maximizes the aggregate present value of Agreement Payments without causing any Payment to be subject to the taxation under Section 4999 of the Code. For purposes of this Section 17, present value shall be determined in accordance with Section 280G(d)(4) of the Code. (b) All determinations to be made under this Section 17 shall be made, in writing, by the Corporation’s independent certified public accountant immediately prior to the Change of Control (the “Accounting Firm”), which firm shall provide its determinations and any supporting calculations in writing to both the Corporation and you within 10 days of the date of termination. Any such determination by the Accounting Firm shall be binding upon the Corporation and you. You shall in your sole discretion determine which and how much of the Agreement Payments shall be eliminated or reduced consistent with the requirements of this Section 17, which determination shall be made by delivery of written notice to the Corporation within 10 days of your receipt of the determination of the Accounting Firm. Within five (5) days after your timely determination, the Corporation shall pay (or cause to be paid) or distribute (or cause to be distributed) to or for the benefit of you, such amounts as are then due to you under this Agreement. In the event you do not make such timely determination then within 15 days after Corporation’s receipt of the determination of the Accounting Firm, the Corporation, in its sole discretion, may pay (or cause to be paid) or distribute (or cause to be distributed) to or for the benefit of you such portion of the Agreement Payments as it may deem appropriate, but no less than the Reduced Amount. (c) As a result of the uncertainty in the application of Section 280G of the Code at the time of the initial determination by the Accounting Firm hereunder, it is possible that Agreement Payments, as the case may be, will have been made by the Corporation which should not have been made (“Overpayment”) or that additional Agreement Payments which have not been made by the Corporation could have been made (“Underpayment”), in each case, consistent with the calculations required to be made hereunder. Within two (2) years after the Separation from Service, the Accounting Firm shall review the determination made by it pursuant to the preceding paragraph. In the event that the Accounting Firm determines that an Overpayment has been made, any such Overpayment shall be treated for all purposes as a loan to you which you shall repay to the Corporation together with interest at the applicable Federal rate provided for in Section 7872(f)(2) of the Code (the “Federal Rate”); provided, however, that no amount shall be payable by you to the Corporation if and to the extent such payment would not reduce the amount which is subject to taxation under Section 4999 of the Code. In the event that the Accounting Firm determines that an Underpayment has occurred, any such Underpayment shall be promptly paid by the Corporation to or for the benefit of you together with interest thereon at the Federal Rate. (d) All of the fees and expenses of the Accounting Firm in performing the determinations referred to in paragraphs (b) and (c) above shall be borne solely by the Corporation. The Corporation agrees to indemnify and hold harmless the Accounting Firm of and from any and all claims, damages and expenses of any nature resulting from or relating to its determinations pursuant to paragraphs (b) and (c) above, except for claims, damages or expenses resulting from the gross negligence or willful misconduct of the Accounting Firm. (e) All payments made to Executive pursuant to this Agreement or otherwise, are subject to and conditioned upon their compliance with applicable laws and any regulations promulgated thereunder.