Local Delivery Network Upgrades. i. If the Interconnection Customer has an Option (A) Generating Facility, the Interconnection Customer shall be entitled to a repayment equal to the total amount the Interconnection Customer paid to the Distribution Provider for the costs of Local Delivery Network Upgrades. ii. If the Interconnection Customer has an Option (B) Generating Facility and has been allocated TP Deliverability and continues to be eligible to retain such TP Deliverability pursuant to Appendix DD of the ISO Tariff, the Interconnection Customer shall be entitled to repayment of a portion of the total amount paid to the Distribution Provider for the costs of Local Delivery Network Upgrades. The repayment amount shall be determined by dividing the amount of TP Deliverability received by the amount of TP Deliverability requested by the Interconnection Customer, and multiplying that percentage by the total amount paid to the Distribution Provider by the Interconnection Customer for Local Delivery Network Upgrades. However, the Interconnection Customer may be entitled to receive Congestion Revenue Rights from the ISO in accordance with the ISO Tariff for that portion of its Local Delivery Network Upgrades that are not covered by cash repayment. iii. If the Interconnection Customer has an Option (B) Generating Facility and has not been allocated any TP Deliverability pursuant to Appendix DD of the ISO Tariff, the Interconnection Customer shall not be entitled to repayment of the amount paid to the Distribution Provider for the costs of Local Delivery Network Upgrades. However, the Interconnection Customer may be entitled to receive Congestion Revenue Rights from the ISO in accordance with the ISO Tariff for the costs of Local Delivery Network Upgrades that are not covered by cash repayment.
Appears in 14 contracts
Sources: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement