Longitudinal Joints. For all layers of pavement except the leveling course, place each layer so that longitudinal construction joints are offset 6 to 12 inches laterally between successive layers. Do not construct longitudinal joints in the wheel paths. The Engineer may waive these requirements where offsetting is not feasible due to the sequence of construction.
Appears in 2 contracts
Sources: Annual Asphalt Concrete Surfacing Services Agreement, Capital Construction Agreement
Longitudinal Joints. For all layers of pavement except the leveling course, place each layer so that longitudinal construction joints are offset 6 to 12 inches laterally between successive layers. Do not construct longitudinal joints in the wheel paths. The Engineer may waive these requirements this requirement where offsetting is not feasible due to the sequence of construction.