Common use of Lump Sum Payment Clause in Contracts

Lump Sum Payment. If an individual JOC Task Order is scheduled for Completion within forty-five (45) days or less, the County will make one payment after thirty (30) days of Work to the Contractor, exclusive of retention. Contractor may request for one payment (including retention payment); however, payment will be made after Final Acceptance of the JOC Task Order.

Appears in 16 contracts

Sources: Job Order Contract, Job Order Contract, Job Order Contract

Lump Sum Payment. If an individual JOC Task Order is scheduled for Completion within forty-forty- five (45) days or less, the County will make one payment after thirty (30) days of Work to the Contractor, exclusive of retention. Contractor may request for one payment (including retention payment); however, payment will be made after Final Acceptance of the JOC Task Order.

Appears in 16 contracts

Sources: Job Order Contract, Job Order Contract, Job Order Contract

Lump Sum Payment. If if an individual JOC Task Order is scheduled for Completion within forty-five (45) 45 days or less, the County will make one payment after thirty (30) 30 days of Work to the Contractor, exclusive of retention. Contractor may request for one payment (including retention payment); however, payment will be made after Final Acceptance of the JOC Task Order.

Appears in 7 contracts

Sources: Job Order Contract for Mechanical Services, Job Order Contract for General Construction Services, Job Order Contract for General Construction Services