Maintenance Scheduling. The Generating Facilities' five year maintenance outage schedule will be provided by GENCO ninety (90) days prior to the commencement of each Contract Year. GENCO will not schedule major maintenance outages in the months of June, July and August, except in the case of System Emergency or by mutual agreement, or in response to unusual circumstances in accordance with Prudent Utility Practice. The Parties recognize that certain non-scheduled routine maintenance will be conducted throughout the year, as required, for the purpose of inspection, cleaning and/or repair of power plant equipment. GENCO will attempt to schedule and implement such outages in the off peak periods. GENCO will inform LIPA when such maintenance is required.