Common use of Make-Ready Survey Clause in Contracts

Make-Ready Survey. A Make-Ready survey must be completed by SBC-13STATE or the Attaching Party before an occupancy permit is issued. The primary purposes of the make ready survey will be to enable SBC-13STATE to 18.3.1 confirm or determine the modifications, capacity expansion, and make-ready work, if any, necessary to accommodate Attaching Party’s attachment of facilities to SBC-13STATE structures; 18.3.2 plan and engineer the facilities modification, capacity expansion, and make-ready work, if any, required to prepare SBC-13STATE’s poles, ducts, conduits, rights-of-way, and associated facilities for Attaching Party’s proposed attachments or occupancy; and 18.3.3 estimate the costs associated with such facilities modification, capacity expansion, or make-ready work.

Appears in 4 contracts

Sources: Interconnection Agreement, Cellular/PCS Interconnection Agreement, CMRS Interconnection Agreement