Manager Laydown and Staging Area. To the extent available based on the particular Project Site, the County shall provide, at no cost to the Manager and on a schedule as reasonably required by the Manager, a supply and material laydown, staging, storage and work force area. The Manager shall be responsible for stabilizing, fencing, providing security and making any additional improvements to the Project Site as may be deemed necessary by the Manager, in order to comply with Permits and Governmental Authorities. At completion of construction, such area shall be returned to its pre-construction condition by the Manager (as modified by the completed Approved Project improvements). If the Manager requires additional material laydown, staging, storage or work force area beyond that provided by the County, the Manager shall be responsible for obtaining the same and providing for such in the Budget Book, and the cost thereof shall be part of Maximum Project Price.