Managing disputes. 32.1 When either Party notifies the other of a dispute, both Parties will attempt in good faith to negotiate a settlement within 20 Working Days. This will include escalation of the dispute to the CCS Representative and the Supplier Representative. 32.2 The obligations of the Parties under this Framework Agreement will not be suspended, ceased or delayed by the reference of a dispute to mediation or arbitration and the Supplier and Supplier’s Staff will continue to comply with the requirements of this Framework Agreement. 32.3 Nothing in this process prevents a Party from seeking any interim order restraining the other Party from, or compelling the other Party to do, any act. 32.4 If the dispute cannot be resolved, the parties will first attempt to settle the matter by mediation and before either party commences formal action.
Appears in 3 contracts
Sources: Framework Agreement, Framework Agreement, Framework Agreement
Managing disputes. 32.1 When either Party notifies the other of a dispute, both Parties will attempt in good faith to negotiate a settlement within 20 Working Days. This will include escalation of the dispute to the CCS Representative Repre- sentative and the Supplier Representative.
32.2 The obligations of the Parties under this Framework Agreement will not be suspended, ceased or delayed by the reference of a dispute to mediation or arbitration and the Supplier and Supplier’s Staff will continue to comply with the requirements of this Framework Agreement.
32.3 Nothing in this process prevents a Party from seeking any interim order restraining the other Party from, or compelling the other Party to do, any act.
32.4 If the dispute cannot be resolved, the parties will first attempt to settle the matter by mediation and before either party commences formal action.
Appears in 1 contract
Sources: Call Off Contract