Materials and Work. 4.1 Unless otherwise specified in this agreement, the Contractor must supply at its own cost everything necessary for the proper completion of the work under this agreement and the proper performance of its obligations under this agreement. 4.2 Unless otherwise specified in this agreement, materials used in the Contract Works and the standard of workmanship must be suitable for their purpose and consistent with the nature and character of the Contract Works. 4.3 Unless otherwise specified in this agreement, materials to be incorporated in the Contract Works must be new and, where applicable, materials and workmanship must comply with the relevant standard of Standards Australia International Limited. 4.4 At any time before the issue of the Final Certificate, the Council may reject any material or work which does not comply with this agreement and may direct its removal, correction or replacement, whether it has been the subject of a payment or not. The Council must make any such rejection or give any such direction as soon as practicable after discovering the non-compliance. 4.5 If the removal, correction or replacement directed by the Council requires the removal of, or damage to, works or materials of other contractors, the Contractor must also remove, replace and/or reinstate those other works or materials. 4.6 If the Council directs the Contractor to correct or replace any material or work, the Contractor must commence the work of correction or replacement within seven days after the receipt by the Contractor of the direction (or such other period as the Council may reasonably determine) and must complete the work properly and to the satisfaction of the Council. If the Council directs the Contractor to remove from the Site any material which does not comply with this agreement, the Contractor must do so promptly. 4.7 The Contractor must bear the cost of all such removals, corrections, replacements and reinstatements. 4.8 If the Contractor fails to comply with this clause the Council may have the removal, correction or replacement carried out by other persons. The cost incurred by the Council in having the work so carried out is a debt due from the Contractor to the Council.
Appears in 2 contracts
Sources: Minor Works Agreement, Works Agreement
Materials and Work.
4.1 Unless otherwise specified in this agreement, the Contractor must supply at its own cost everything necessary for the proper completion of the work under this agreement and the proper performance of its obligations under this agreement.
4.2 Unless otherwise specified in this agreement, materials used in the Contract Works and the standard of workmanship must be suitable for their purpose and consistent with the nature and character of the Contract Works.
4.3 Unless otherwise specified in this agreement, materials to be incorporated in the Contract Works must be new and, where applicable, materials and workmanship must comply with the relevant standard of Standards Australia International Limited.
4.4 At any time before the issue of the Final Certificate, the Council may reject any material or work which does not comply with this agreement and may direct its removal, correction or replacement, whether it has been the subject of a payment or not. The Council must make any such rejection or give any such direction as soon as practicable after discovering the non-compliance.
4.5 If the removal, correction or replacement directed by the Council requires the removal of, or damage to, works or materials of other contractors, the Contractor must also remove, replace and/or reinstate those other works or materials.
4.6 If the Council directs the Contractor to correct or replace any material or work, the Contractor must commence the work of correction or replacement within seven days after the receipt by the Contractor of the direction (or such other period as the Council may reasonably determine) and must complete the work properly and to the satisfaction of the Council. If the Council directs the Contractor to remove from the Site any material which does not comply with this agreement, the Contractor must do so promptly.
4.7 The Contractor must bear the cost of all such removals, corrections, replacements and reinstatements.
4.8 If the Contractor fails to comply with this clause the Council may have the removal, correction or replacement carried out by other persons. The cost incurred by the Council in having the work so carried out is a debt due from the Contractor to the Council.
Appears in 1 contract
Sources: Minor Works Agreement
Materials and Work. 4.1 10.1 Unless otherwise specified in this agreement, the Contractor Supplier must supply at its own cost everything necessary for the proper completion of the work under this agreement and the proper performance of its obligations under this agreement.
4.2 10.2 Unless otherwise specified in this agreement, materials used in the Contract Works and the standard of workmanship must be suitable for their purpose and consistent with the nature and character of the Contract Works.
4.3 10.3 Unless otherwise specified in this agreement, materials to be incorporated in the Contract Works must be new and, where applicable, materials and workmanship must comply with the relevant standard of Standards Australia International Limited.
4.4 10.4 At any time before the issue of the Final Certificate, the Council may reject any material or work which does not comply with this agreement and may direct its removal, correction or replacement, whether it has been the subject of a payment or not. The Council must make any such rejection or give any such direction as soon as practicable after discovering the non-non- compliance.
4.5 10.5 If the removal, correction or replacement directed by the Council requires the removal of, or damage to, works or materials of other contractors, the Contractor Supplier must also remove, replace and/or reinstate those other works or materials.
4.6 10.6 If the Council directs the Contractor Supplier to correct or replace any material or work, the Contractor Supplier must commence the work of correction or replacement within seven days after the receipt by the Contractor Supplier of the direction (or such other period as the Council may reasonably determine) and must complete the work properly and to the satisfaction of the Council. If the Council directs the Contractor Supplier to remove from the Site any material which does not comply with this agreement, the Contractor Supplier must do so promptly.
4.7 10.7 The Contractor Supplier must bear the cost of all such removals, corrections, replacements and reinstatements.
4.8 10.8 If the Contractor Supplier fails to comply with this clause the Council may have the removal, correction or replacement carried out by other persons. The cost incurred by the Council in having the work so carried out is a debt due from the Contractor Supplier to the Council.
Appears in 1 contract
Sources: Construction Contract
Materials and Work. 4.1 5.1 Unless otherwise specified in this agreement, the Contractor must supply at its own cost everything necessary for the proper completion of the work Works under this agreement Agreement and the proper performance of its obligations under this agreementAgreement.
4.2 5.2 Unless otherwise specified in this agreementAgreement, materials used in the Contract Works and the standard of workmanship must be suitable for their purpose and consistent with the nature and character of the Contract Works.
4.3 5.3 Unless otherwise specified in this agreementAgreement, materials to be incorporated in the Contract Works must be new and, where applicable, materials and workmanship must comply with the relevant standard of Standards Australia International Limited.
4.4 5.4 At any time before the issue of the Final Certificate, the Council may reject any material or work which does not comply with this agreement Agreement and may direct its removal, correction or replacement, whether it has been the subject of a payment or not. The Council must make any such rejection or give any such direction as soon as practicable after discovering the non-compliance.
4.5 5.5 If the removal, correction or replacement directed by the Council requires the removal of, or damage to, works or materials of other contractors, the Contractor must also remove, replace and/or reinstate those other works or materials.
4.6 5.6 If the Council directs the Contractor to correct or replace any material or work, the Contractor must commence the work of correction or replacement within seven days after the receipt by the Contractor of the direction (or such other period as the Council may reasonably determine) and must complete the work properly and to the satisfaction of the Council. If the Council directs the Contractor to remove from the Site any material which does not comply with this agreementAgreement, the Contractor must do so promptly.
4.7 5.7 The Contractor must bear the cost of all such removals, corrections, replacements and reinstatements.
4.8 5.8 If the Contractor fails to comply with this clause the Council may have the removal, correction or replacement carried out by other persons. The cost incurred by the Council in having the work so carried out is a debt due from the Contractor to the Council.
5.9 All valuable minerals, fossils, articles or objects of antiquity or of anthropological or archaeological interest and articles of value found on Site belong to the Council. Immediately upon discovery of such things, the Contractor must take precautions to prevent the loss, removal or damage of such materials and must immediately notify the Council in writing.
Appears in 1 contract
Sources: Works Agreement