MEASUREMENT OF QUANTITIES. All work to be paid for at a contract price per unit of measurement shall be measured by the Superintending Engineer in accordance with the methods set forth in the relevant specifications. Quantities of material wasted or disposed off in a manner not called for under the contract, or rejected material whether placed- or not or materials placed outside of the lines indicated on the plans or given by the: Superintending Engineering or material remaining on hand after completion of the work will not be measured or paid for. No compensation will be allowed for hauling back materials.