Method of Acceptance or Rejection Sample Clauses

The "Method of Acceptance or Rejection" clause defines the procedures by which a party must formally accept or reject goods, services, or contractual terms. Typically, this clause outlines the timeframe and manner in which acceptance or rejection must be communicated, such as requiring written notice within a specified number of days after delivery or performance. By establishing clear steps and deadlines, this clause helps prevent disputes over whether obligations have been met and ensures both parties understand how and when decisions regarding acceptance or rejection should be made.
Method of Acceptance or Rejection. (a) Upon notification by the SELLER of the completion of the Trial Run of the VESSEL and submission to the BUYER of the detailed written results thereof, the BUYER or the BUYER's Supervisor shall within six (6) New York business days thereafter, notify the SELLER by telefax confirmed in writing of its acceptance of the VESSEL if the BUYER agrees that the VESSEL conforms with the requirements of this Contract and the Specifications. (b) However, should the VESSEL or any part thereof including its equipment not conform to the requirements of this Contract and the Specifications, and the BUYER shall give notice of rejection to the SELLER for such reason, then the SELLER shall investigate with the Supervisor the cause of failure and proper steps shall be taken to remedy the same and shall make whatever corrections and alterations and/or re-Trial Run or Runs as may be necessary without extra cost to the BUYER, and upon notification by the SELLER of completion of such alterations or corrections and/or re-Trial or re-Trials and submission to the BUYER of the detailed written results thereof the BUYER shall, within six (6) New York business days thereafter, again notify the SELLER by telefax confirmed in writing of its acceptance of the VESSEL or of the rejection of the VESSEL together with the reason therefor. This process shall be repeated until the earlier of the BUYER’s acceptance of the VESSEL or the rescission of this Contract in accordance with its terms. (c) In the event that the BUYER fails to notify the SELLER by telefax confirmed in writing of its acceptance or rejection of the VESSEL together with the reason therefor within six (6) New York business days period as provided for in the above sub-paragraphs (a) and (b), the BUYER shall be deemed to have accepted the VESSEL. (d) Any dispute arising among the parties hereto as to the result of any of the Trial Run or further tests or trials, as the case may be, of the VESSEL shall be solved by reference to arbitration as provided in Article XIII hereof. (e) It is agreed that the BUYER shall not be entitled to reject the VESSEL by reason of any minor or insubstantial defects or deficiencies judged from the point of view of international shipbuilding standards as not being in conformity with the Specifications but in such case the SELLER shall be obliged to remedy such defects or deficiencies if any before effecting delivery of the VESSEL to the BUYER under this Contract.
Method of Acceptance or Rejection. (a) Upon completion of the trial run, the SELLER shall give the BUYER a notice by telex or facsimile confirmed in writing of completion of the trial run and promptly provide the BUYER with all protocols and records of tests and trials, as and if the SELLER considers that the results of the trial run prove conformity of the VESSEL to this Contract and Specifications. The BUYER shall, within six (6) working days after receipt of the aforementioned records of tests and trials from the SELLER, notify the SELLER by telex or facsimile confirmed in writing of its acceptance or rejection of the VESSEL’s conformity to this Contract and the Specifications. (b) Should the records of tests and trials indicate that the VESSEL does not conform to the requirements of this Contract or the Specifications and if the SELLER agrees with the BUYER’s notice of non-conformity, then the SELLER shall promptly take the necessary steps to correct such non-conformity and notify the BUYER promptly in writing or by telex or facsimile confirmed in writing advising the BUYER of the estimated additional time required for the necessary alterations to correct such non-conformity. Upon completion of correction of such non-conformity, new trial run or runs as necessary will be made to prove conformity of the VESSEL to this Contract and Specifications if so found necessary by the SELLER, the Classification Society and the Representatives. The SELLER shall notify the BUYER of the time and place of any new trial run no less than five (5) working days beforehand, unless otherwise mutually agreed to. All provisions of the trial run shall apply to such new trial run. Notwithstanding the aforesaid, the BUYER may accept the VESSEL qualifying its acceptance by reservations regarding works or parts which have not been completed or properly installed prior to such acceptance. In the event that BUYER makes such qualified acceptance the parties will reach an agreement in writing, prior to the delivery of the VESSEL, as to how and when to remedy the items being the subject of the qualified acceptance, at the SELLER’s cost and expense, either before or after the delivery, as quickly as possible, without delaying the date of delivery and without causing the BUYER inconvenience in the operation of the VESSEL. (c) In the event that the SELLER fails to correct any non-conformity of which it has been given notice by the BUYER, which non-conformity has been confirmed by the Classification Society, the BUYER shall...
Method of Acceptance or Rejection. (a) If during any sea trials any breakdowns occur entailing interruption or irregular performance which can be repaired on board, the trial shall be continued after repairs and be valid in all respects. If such repair is temporarily made to continue sea trials, the Builder will inspect the repaired part after sea trials to assure that it complies with the Specifications. However, if such interruption or irregular performance occurs more than two times on the same items, then such item(s) should be identified by the Builder to the Buyer as soon as practicably possible, and inspected/corrected by the Builder as soon as practicably possible. In the meantime, the inspection result, which will be final or preliminary as the case may be, should be given to the Buyer before the delivery of the Vessel. (b) As soon as practicable after satisfactory completion of the trial run, Builder shall give Buyer a written report thereon and written notice that Builder considers that the results of the trial run indicate conformity of the Vessel to this Contract and the Specifications. Buyer shall, within three (3) Business Days after receipt of such notice from Builder, notify Builder of its acceptance or rejection of the Vessel on the basis of its conformity or non-conformity with the requirements of this Contract and the Specifications. (c) If the results of the trial run indicate that the Vessel, or any part or equipment thereof, does not conform to the requirements of this Contract and/or the Specifications, then, Builder shall take the necessary steps to correct such non-conformity. Upon completion of correction of such non-conformity, Builder shall give Buyer notice thereof. Buyer shall, within three (3) days after receipt of such notice from Builder notify Builder of its acceptance or rejection of the Vessel. However, Buyer shall not be entitled to reject the Vessel by reason of any minor or insubstantial defect or non-conformity judged from the viewpoint of standard shipbuilding practice but in such case, the Builder shall not be released from its obligation to correct and/or remedy such minor or insubstantial non-conformity as far as practicable during the Warranty Period. (d) If Buyer considers that the results of the trial run indicate that the Vessel or any part or equipment thereof does not conform to this Contract and/or the Specifications, Buyer shall indicate in detail in a notice of rejection in what respect the Vessel or any part or equipment thereof, does n...
Method of Acceptance or Rejection. (a) If during any sea trials any breakdowns occur entailing interruption or irregular performance which can be repaired on board, the trial shall be continued after repairs and be valid in all respects. If such repair is temporarily made to continue sea trials, the Builder will inspect the repaired part after sea trials to assure that it complies with the
Method of Acceptance or Rejection. (a) Upon completion of the trial run, the BUILDER shall give the BUYER a notice in writing of completion, if the BUILDER considers that the results thereof demonstrate that the VESSEL conforms to this Contract and the Specifications. The BUYER shall, within 24 hours after receipt of such notice, notify the BUILDER in writing of its acceptance or rejection of the VESSEL. (b) If the results of the trial run demonstrate that the VESSEL or any part or equipment thereof does not conform to the requirements of this Contract or the Specifications, or the BUILDER agrees to the BUYER’s notice of rejection, the BUILDER shall take all necessary steps to correct such non-conformity. If necessary, a further trial run shall be carried put and new notice issued in accordance with (a) above. (c) If the BUYER for any reason rejects the VESSEL, the BUYER shall in his written notice of rejection give particulars of its reason therefore in such detail as can be reasonably required. (d) If the BUILDER disputes the rejection by the BUYER, the case shall be submitted for final decision by arbitration in accordance with Article XVIII hereof, unless the Parties agree otherwise. (e) Failure in responding to the notice given under (a) above shall be deemed as acceptance of the VESSEL. Ulstein Verft AS ▇.▇. ▇▇▇ ▇▇▇, ▇-▇▇▇▇ ▇▇▇▇▇▇▇▇▇▇, ▇▇▇▇▇▇ Tel. +▇▇ ▇▇▇▇ ▇▇▇▇. Fax +▇▇ ▇▇▇▇ ▇▇▇▇ Ent. No: 912 447 561 ▇▇▇.▇▇▇▇▇▇▇.▇▇▇
Method of Acceptance or Rejection. (a) If, during any Trial, any breakdown occurs entailing interruption or irregular performance which can be repaired on board, the Trial shall continue after completion of the relevant repairs. However, if the Vessel must return to the Shipyard or enter any other port or shipyard to enable the breakdown to be remedied or repaired, that Trial, or part of that Trial, shall be undertaken again in accordance with Clause 7.1(c). In the event that, during or after any Trial, it becomes apparent that the Vessel has failed or will fail to meet the requirements of this Contract and the Specifications, Builder shall promptly notify Buyer and shall advise Buyer of the estimated additional time required to enable Builder to correct such deficiency. (b) Upon completion of each Trial and each post-Trial inspection, Builder shall provide to Buyer (with a copy to Charterer): (i) a written report of each Trial and post-Trial inspection containing the results of the relevant Trial and Builder’s observations during any post-Trial inspection; and (ii) a notice stating whether Builder considers that the results of the relevant Trial confirm conformity of the Vessel to this Contract and the Specifications in relation to any part of the Vessel that has been tested during such Trial.
Method of Acceptance or Rejection. (a) Upon completion of the Tests and Trials, the BUILDER shall give the BUYER notice in accordance with Article XXII of completion of the Tests
Method of Acceptance or Rejection. (a) Upon satisfactory completion of the trials in terms of this Article, the Buyer shall immediately thereafter confirm in writing his acceptance of such completion of the trials. In case of non-acceptance the Buyer shall indicate in writing in what respect of the trials, the Vessels or any part thereof does not conform to the Specifications. The Builder shall rectify such Non-conformity at its own expense and perform such further tests as may be deemed necessary and prove to the satisfaction of the Regulatory Body/Statutory Authority/Classification Society/the Buyer that the requirements of the Specifications are complied with. The Builder will not be entitled to any extension of the Date of Delivery or for any increase in cost of the Vessels on this account. (b) The Buyer shall not be obliged to take delivery of the Vessels if it is not fully in conformity with the specifications including its agreed amendments, or if there are any conditions or recommendations made by the Classification Society and/or Regulatory Bodies or owners authorized representative. However, if the deficiencies or the conditions/recommendations are of minor importance, and the Builder is unable to comply the same within a reasonable time, the Builder may nevertheless require the Buyer to take delivery of the Vessel, provided the Builder undertakes to make good the deficiency or fulfil the requirement within the guarantee period.
Method of Acceptance or Rejection. Effect of Acceptance: a. Acceptance of the VESSEL as above provided shall be final and binding and the VESSEL will be deemed to be in conformity with the Contract. The BUYER shall not refuse formal delivery of the VESSEL as hereinafter provided, if the BUILDER complies with all other procedural requirements for delivery as provided in Article VII hereof. b. If minor work or items on the VESSEL are incomplete or missing when the VESSEL otherwise is ready for delivery and such work or items do not materially affect the operation of the VESSEL nor are likely to cause damage or excessive deterioration to the VESSEL, the BUYER shall not withhold its consent to accept delivery of the VESSEL subject to the right of the BUYER to have such items completed by the BUILDER in a reasonable manner and period of time. The parties shall on delivery execute a protocol of outstanding work and a schedule for completion of such work.

Related to Method of Acceptance or Rejection

  • Acceptance or Rejection All Goods, Services, and Deliverables are subject to acceptance by the JBE. The JBE may reject any Goods, Services or Deliverables that (i) fail to meet applicable acceptance criteria, (ii) are not as warranted, or (iii) are performed or delivered late (without prior consent by the JBE). If the JBE rejects any Good, Service, or Deliverable (other than for late performance or delivery), Contractor shall modify such rejected Good, Service, or Deliverable at no expense to the JBE to correct the relevant deficiencies and shall redeliver such Good, Service, or Deliverable to the JBE within ten (10) business days after the JBE’s rejection, unless otherwise agreed in writing by the JBE. Thereafter, the parties shall repeat the process set forth in this section until the JBE accepts such corrected Good, Service, or Deliverable. The JBE may terminate that portion of this Agreement which relates to a rejected Good, Service, or Deliverable at no expense to the JBE if the JBE rejects that Good, Service, or Deliverable (i) for late performance or delivery, or (ii) on at least two (2) occasions for other deficiencies. Description of Services or Deliverables provided by Contractor: _____________________________________ Date submitted to the JBE:_____________ The Services or Deliverables are:

  • Acceptance or Rejection of Subscription (a) I understand and agree that the Company reserves the right to reject this subscription for the Units, in whole or in part, for any reason and at any time prior to the Closing, notwithstanding prior receipt by me of notice of acceptance of my subscription. (b) In the event of the rejection of this subscription, my subscription payment will be promptly returned to me without interest or deduction and this Subscription Agreement shall have no force or effect. In the event my subscription is accepted and the offering is completed, the funds specified above shall be released to the Company.

  • ACCEPTANCE AND REJECTION a. Buyer shall accept the Services or give Seller notice of rejection within a reasonable time after the date of delivery. No payment, prior test, inspection, passage of title, any failure or delay in performing any of the foregoing, or failure to discover any defect or other nonconformance shall relieve Seller of any obligations under this Contract or impair any rights or remedies of Buyer. b. If Seller delivers defective or non-conforming Services, Buyer may at its option and at Seller's expense: (i) require Seller to promptly reperform, correct or replace the Services; (ii) correct the Services; or (iii) obtain replacement Services from another source. Return to Seller of defective or non-conforming Services and redelivery to Buyer of corrected or replaced Services shall be at Seller's expense. c. Seller shall not redeliver corrected or rejected Services without disclosing the former rejection or requirement for correction. Seller shall disclose any corrective action taken. All repair, replacement and other correction and redelivery shall be completed as Buyer may reasonably direct.

  • INSPECTION, ACCEPTANCE AND REJECTION a. All shipments of Goods and performance of Services shall be subject to Buyer’s right of inspection. Buyer shall have ninety (90) days (the “Inspection Period“) following the delivery of the Goods at the Delivery Point or performance of the Services to undertake such inspection, and upon such inspection Buyer shall either accept the Goods or Services (“Acceptance“) or reject them. Buyer shall have the right to reject any Goods that are delivered in excess of the quantity ordered or are damaged or defective. In addition, Buyer shall have the right to reject any Goods or Services that are not in conformance with the Specifications or any term of this Agreement. Transfer of title to Buyer of Goods shall not constitute Buyer’s Acceptance of those Goods. Buyer shall provide Supplier within the Inspection Period notice of any Goods or Services that are rejected, together with the reasons for such rejection. If Buyer does not provide Supplier with any notice of rejection within the Inspection Period, then Buyer will be deemed to have provided Acceptance of such Goods or Services. Buyer’s inspection, testing, or Acceptance or use of the Goods or Services hereunder shall not limit or otherwise affect Supplier’s warranty obligations hereunder with respect to the Goods or Services, and such warranties shall survive inspection, test, Acceptance and use of the Goods or Services. b. Buyer shall be entitled to return rejected Goods to Supplier at Supplier’s expense and risk of loss for, at Buyer’s option, either: (i) full credit or refund of all amounts paid by Buyer to Supplier for the rejected Goods; or (ii) replacement Goods to be received within the time period specified by Buyer. Title to rejected Goods that are returned to Supplier shall transfer to Supplier upon such delivery and such Goods shall not be replaced by Supplier except upon written instructions from Buyer. Supplier shall not deliver Goods that were previously rejected on grounds of non-compliance with this Agreement, unless delivery of such Goods is approved in advance by Buyer, and is accompanied by a written disclosure of Buyer’s prior rejection(s).

  • Acceptance; Rejection A holder of Notes may accept the offer to prepay made pursuant to this Section 8.8 by causing a notice of such acceptance to be delivered to the Company not later than 15 Business Days after receipt by such holder of the most recent offer of prepayment. A failure by a holder of Notes to respond to an offer to prepay made pursuant to this Section 8.8 shall be deemed to constitute rejection of such offer by such holder.