Milestone Payment Basis. 26.1 Where the applicable payment mechanism is "Milestone Payment", invoice(s) shall be submitted for the amount(s) indicated in Annex B as and when the relevant milestone is achieved in its final form by the Supplier or following completion of the Services, as the case may be, indicating both the amount or amounts due at the time and cumulatively. 26.2 Payments pursuant to clause 26.1 are subject to the satisfaction of the Project Officer in relation to the performance by the Supplier of its obligations under the Calldown Contract and to verification by the Project Officer that all prior payments made to the Supplier under this Calldown Contract were properly due.
Appears in 1 contract
Sources: Framework Agreement
Milestone Payment Basis. 26.1 28.1 Where the applicable payment mechanism is "Milestone Payment", invoice(s) shall be submitted for the amount(s) indicated in Annex B as and when the relevant milestone is achieved in its final form by the Supplier or following completion of the Services, as the case may be, indicating both the amount or amounts due at the time and cumulatively.
26.2 . Payments pursuant to clause 26.1 28.1 are subject to the satisfaction of the Project Officer in relation to the performance by the Supplier of its obligations under the Calldown Contract and to verification by the Project Officer that all prior payments made to the Supplier under this Calldown Contract were properly due.
Appears in 1 contract
Sources: Calldown Contract