Common use of Minor Changes Clause in Contracts

Minor Changes. The A/E, with concurrence of the ODR, will have authority to order minor changes in the Work not involving an adjustment in the Contract Sum or an extension of the Contract Time. Such changes shall be effected by written order which the Contractor shall carry out promptly and record on as-built record documents.

Appears in 31 contracts

Sources: Construction Management Agreement, Construction Management Agreement, Construction Management Agreement

Minor Changes. The A/E, with concurrence of the ODR, will have authority to order minor changes in the Work not involving an adjustment in the Contract Sum or an extension of the Contract Time. Such changes shall be effected by written order which the Contractor shall carry out promptly and record on as-built record documentsthe Record Documents.

Appears in 22 contracts

Sources: Construction Services Agreement, Construction Services Agreement, Construction Manager at Risk Agreement

Minor Changes. The A/E, with concurrence of the ODR, will have authority to order minor changes in the Work not involving an adjustment in the Contract Sum or an extension of the Contract Time. Such changes shall be effected by written order which the Contractor shall carry out promptly and record on as-built record documents.

Appears in 7 contracts

Sources: General Construction Services Contract, Job Order, General Construction Services Contract

Minor Changes. The A/E, with concurrence of the ODR, will have authority to order minor changes in the Work not involving an adjustment in the Contract Sum or an extension of the Contract Time. Such changes shall be effected by written order which the Contractor shall carry out promptly and record on as-as- built record documentsdocuments the Record Documents.

Appears in 6 contracts

Sources: Design/Build Agreement, Construction Contract, Construction Contract

Minor Changes. The A/E, with concurrence of the ODR, will have authority to order minor changes in the Work not involving an adjustment in the Contract Sum or an extension of the Contract Time. Such changes shall be effected affected by written order which the Contractor shall carry out promptly and record on as-built record documentsRecord Documents.

Appears in 2 contracts

Sources: Owner and Contractor Agreement, Construction Contract