Modifications to the Unit. The Interconnection Customer may request a Modification at any time after commencement of parallel operation. T&D Manager shall evaluate the request and determine whether the proposed change is a Material Modification in accordance with the rules for requesting changes to applications in the SGIP. A Material Modification will be studied pursuant to the procedures in the SGIP for new applications. In the case of a non-material modification that is accepted by T&D Manager, the Parties will execute an amendment to this Agreement describing the Unit changes that have been approved.