MONITORING OF CONSTRUCTION. 11.5.1. During construction of the Project, the Concessionaire shall furnish monthly progress reports to the Engineer-in-Charge on the progress of Construction Works, i.e., planned v/s actual progress highlighting the delays along with reasons for delay, EHS standards followed, any shortcomings, near-miss incidence and shall also give such other relevant information as may be required by the Authority. The monthly progress reports shall be submitted no later than 7 (seven) days after the close of each month; 11.5.2. Samples of all products to be used shall be submitted to the Authority. Any damage during construction, to any part of the work, for any reasons, due to rain, storm, or neglect of the Concessionaire, shall be rectified by the Concessionaire, in an approved manner; 11.5.3. During the Construction Period, the Engineer-in-Charge or his/her representative shall inspect the Project at least once in a month and make a report of such inspection the defects or deficiencies, if any, with particular reference to the Scope of Work, the progress of construction, the status of compliance with the Construction Plan and Designs and Drawings. It shall send a report within 7 days of such inspection to the Concessionaire and upon receipt thereof, the Concessionaire shall rectify and remedy the defects and the deficiencies, if any, stated in the Inspection Report. However, such inspections or the submission of Inspection Report by the Engineer-in-Charge shall not relieve or absolve the Concessionaire of its obligations and liabilities, as per the provisions of the Agreement, in any manner whatsoever; 11.5.4. All equipment/machinery/software programs/ applications covered under the Project shall be subjected to inspection / testing by the Engineer-in-Charge or his/her representative on completion & commissioning; and 11.5.5. If the Project In-Charge of the Authority has reasonably determined that the rate of progress of works is such that the Project is not likely to be completed by the Scheduled Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Project-in-Charge in reasonable detail about the steps it proposes to take to expedite the progress and the period within which it shall achieve COD.
Appears in 2 contracts
Sources: Concession Agreement, Concession Agreement
MONITORING OF CONSTRUCTION. 11.5.112.5.1. During construction of the Project, the Concessionaire shall furnish monthly progress reports to the Engineer-in-Charge Independent Engineer on the progress of Construction Works, i.e., planned v/s actual progress highlighting the delays along with reasons for delay, EHS standards followed, any shortcomings, near-miss incidence Works and shall also give such other relevant information as may be required by the Independent Engineer or by the Authority. The monthly progress reports shall be submitted no later than 7 (seven) days after the close of each month;
11.5.212.5.2. Samples of all products to be used shall be submitted to the AuthorityAuthority when so directed. Any damage during construction, to any part of the work, for any reasons, due to rain, storm, or neglect of the Concessionaire, shall be rectified by the Concessionaire, in an approved manner;
11.5.312.5.3. During the Construction Period, the Engineer-in-Charge or his/her representative Independent Engineer shall inspect the Project at least once in a month and make a report of such inspection the defects or deficiencies, if any, with particular reference to the Scope of Workthe Project, the progress of construction, defects or deficiencies, if any, the status of compliance with the Construction Plan and Designs Specifications and DrawingsStandards. It shall send a report within 7 days of such inspection to the Concessionaire and upon receipt thereof, the Concessionaire shall rectify and remedy the defects and the deficiencies, if any, stated in the Inspection Report. However, such inspections or the submission of Inspection Report by the Engineer-in-Charge Independent Engineer shall not relieve or absolve the Concessionaire of its obligations and liabilities, as per the provisions of the Agreement, in any manner whatsoever;
11.5.412.5.4. All equipment/machinery/software programs/ applications covered under the Project shall be subjected to inspection / testing by the Engineer-in-Charge or his/her representative Independent Engineer on completion & commissioning; and
11.5.512.5.5. If the Project In-Charge of the Authority Independent Engineer has reasonably determined that the rate of progress of works is such that the Project is not likely to be completed by the Scheduled Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Project-in-Charge Independent Engineer in reasonable detail about the steps it proposes to take to expedite the progress and the period within which it shall achieve COD.
Appears in 2 contracts
Sources: Concession Agreement, Concession Agreement
MONITORING OF CONSTRUCTION. 11.5.112.4.1. During construction of the Project, the Concessionaire shall furnish monthly progress reports to the Engineer-in-Charge Authority or his Representative on the progress of Construction Worksconstruction works, i.e., planned v/s actual progress highlighting the delays along with reasons for delay, EHS standards followed, any shortcomings, near-miss incidence and shall also give such other relevant information as may be required by the AuthorityAuthority or his Representative. The Concessionaire should also include planning for procurement of material and reflect the same in the program chart so that there is no delay in completion of the Project. The monthly progress reports shall be submitted no later than 7 (seven) days after the close of each month;
11.5.212.4.2. Samples of all products to be used shall be submitted to the AuthorityAuthority / his Representative when so directed. Any damage during construction, to any part of the work, for any reasons, due to rain, storm, or neglect of the Concessionaire, shall be rectified by the Concessionaire, in an approved manner;
11.5.312.4.3. During the Construction Period, the EngineerAuthority’s Project In-in-Charge charge or his/her his representative shall inspect the Project at least once in a month fortnight and make a report of such inspection the defects or deficiencies, if any, with particular reference to the Scope of Work, the progress of construction, the status of compliance with the Construction Plan Project and Designs and DrawingsSpecifications & Standards. It shall send a report within 7 days of such inspection to the Concessionaire and upon receipt thereof, the Concessionaire shall rectify and remedy the defects and the deficiencies, if any, stated in the Inspection Report. However, such inspections or the submission of Inspection Report by the Engineer-in-Project in- Charge or his representative shall not relieve or absolve the Concessionaire of its obligations and liabilities, as per the provisions of the Agreement, in any manner whatsoever;
11.5.412.4.4. All equipment/machinerysoftware programs/software programs/ applications covered under the Project shall be subjected to inspection / testing by the EngineerProject In-in-Charge charge or his/her his representative on completion & commissioning; and
11.5.512.4.5. If the Project In-Charge of the Authority has reasonably determined that the rate of progress of works is such that the Project is not likely to be completed by the Scheduled Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Project-in-Charge in reasonable detail about the steps it proposes to take to expedite the progress and the period within which it shall achieve COD.
Appears in 1 contract
Sources: Concession Agreement