MONITORING OF CONSTRUCTION. 13.1 Monthly progress reports 13.1.1 Until the COD of Phase I, the Concessionaire shall, within 7 (seven) days after the close of each month, furnish to the Authority and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Authority and/or Independent Engineer. 13.1.2 Notwithstanding anything to the contrary contained in this Agreement, the Authority shall have the right, but not the obligation, to appoint at its cost from time to time and at any time, the additional engineers, including any Government owned entity or Government employee to inspect and monitor the Construction Works.