Common use of Monthly Planning; Rolling Forecast Clause in Contracts

Monthly Planning; Rolling Forecast. For planning purposes only, no later than the third (3rd) Business Day of each calendar month, Suntech shall deliver to MEMC a forecast of the quantities of Wafers that Suntech anticipates that it will order from MEMC over the subsequent rolling twelve (12) months. Such rolling forecasts are for capacity planning purposes only, and such estimated amounts in the rolling forecasts shall have no effect on Suntech’s obligation to purchase some or all of Suntech’s Yearly Minimum Quantity for any Contract Year or MEMC’s obligation to deliver the indicated quantities, unless such quantity is confirmed pursuant to the procedures of Section 2.3.

Appears in 2 contracts

Sources: Solar Wafer Supply Agreement (Suntech Power Holdings Co., Ltd.), Solar Wafer Supply Agreement (Memc Electronic Materials Inc)