Monthly Progress Reporting. The Consultant submits to the Employer Agent a monthly report following the assessment date, but by no later than the last day of each month. The report contains the following information as a minimum requirement: 2.14.7.1 Executive summary. (Narrative identifying major movement within the reporting period.) 2.14.7.2 A four-week look ahead work window focussing on Employer activities due to start and due for Completion. 2.14.7.3 Revised programme for Employer’s Agent acceptance indicating, actual progress of work against last Accepted Programme. 2.14.7.4 Updated "Project List of Applicable Documents" which is a list (table) indicating the “current accepted” revision as well as the status of any later revisions of the specific document. Documentation to be covered by the Task List of Applicable Documents (TLAD) include the following as a minimum: 2.14.7.5 Contract Quality Management Plan / Task Quality Plan 2.14.7.6 List of activities which: • were completed during current reporting period, (including the activities of the Employer and Others), • are in progress (including the activities of the Employer and Others), • are to be undertaken during the next reporting period per discipline, (including the activities of the • Are behind schedule together with an action plan on how the delays are to be rectified. 2.14.7.7 Shows results obtained, range of application and validation. 2.14.7.8 Shows the relationship of results to previous findings/theories/technological developments. 2.14.7.9 Identifies the description of apparatus, operations and data gathering activities.
Appears in 1 contract
Sources: Professional Services
Monthly Progress Reporting. The Consultant submits to the Employer Agent agent a monthly report following the assessment date, but by no later than the last day of each month. The report contains the following information as a minimum requirement:
2.14.7.1 4.9.7.1 Executive summary. (Narrative identifying major movement within the reporting period.)
2.14.7.2 4.9.7.2 A four-week look ahead work window focussing on Employer activities due to start and due for Completion.
2.14.7.3 4.9.7.3 Revised programme for Employer’s Agent acceptance indicating, actual progress of work against last Accepted Programme.
2.14.7.4 4.9.7.4 Updated "Project List of Applicable Documents" which is a list (table) indicating the “current accepted” revision as well as the status of any later revisions of the specific document. Documentation to be covered by the Task List of Applicable Documents (TLAD) include the following as a minimum:
2.14.7.5 Contract Quality Management Plan / 4.9.7.5 Contract/Task Quality Plan
2.14.7.6 4.9.7.6 List of activities which: • were completed during current reporting period, (including the activities of the Employer and Others), • are in progress (including the activities of the Employer and Others), • are to be undertaken during the next reporting period per discipline, (including the activities of the • Employer and Others), Are behind schedule together with an action plan on how the delays are to be rectified.
2.14.7.7 4.9.7.7 Shows results obtained, range of application and validation.
2.14.7.8 4.9.7.8 Shows the relationship of results to previous findings/theories/technological developments.
2.14.7.9 4.9.7.9 Identifies the description of apparatus, operations and data gathering activities.
4.9.7.10 Provides descriptions of significant problems that occurred.
4.9.7.11 Provides a summary of work performed including recommendations and description of possible impacts.
4.9.7.12 Indicates deviations from plan, recorded and analysed.
4.9.7.13 Proposed monthly assessment information for the current reporting period.