MUTUAL RESPONSIBILITY. 6.2.1 The Construction Manager shall afford the Owner and separate contractors reasonable opportunity for introduction and storage of their materials and equipment and performance of their activities and shall connect and coordinate the Construction Manager's construction and operations with theirs as required by the Contract Documents. 6.2.2 If part of the Construction Manager's Work depends for proper execution or results upon construction or operations by the Owner or a separate contractor, the Construction Manager shall, prior to proceeding with that portion of the Work, promptly report to the Architect and Development Manager apparent discrepancies or defects in such other construction that would render it unsuitable for such proper execution and results. Failure of the Construction Manager to so report shall constitute an acknowledgment that the Owner's or separate contractor's completed or partially completed construction is fit and proper to receive the Construction Manager's Work, except as to defects not then reasonably discoverable. 6.2.3 The Owner shall be reimbursed by the Construction Manager for costs incurred by the Owner which are payable to a separate contractor because of delays, improperly timed activities or defective construction of the Construction Manager. 6.2.4 The Construction Manager shall promptly remedy damage wrongfully caused by the Construction Manager to completed or partially completed construction or to property of the Owner or separate contractors as provided in Subparagraph 10.2.5. 6.2.5 The Owner and each separate contractor shall have the same responsibilities for cutting and patching as are described for the Construction Manager in Paragraph 3.14.
Appears in 2 contracts
Sources: Agreement Between Owner and Architect (Chukchansi Economic Development Authority), Construction Manager Agreement (Chukchansi Economic Development Authority)
MUTUAL RESPONSIBILITY. 6.2.1 The Construction Manager Contractor shall afford the Owner and separate contractors reasonable opportunity for introduction and storage of their materials and equipment and performance of their activities activities, and shall connect and coordinate the Construction ManagerContractor's construction and operations with theirs as required by the Contract Documents.
6.2.2 If part of the Construction ManagerContractor's Work depends for proper execution or results upon construction or operations by the Owner or a separate contractor, the Construction Manager Contractor shall, prior to proceeding with that portion of the Work, promptly report to the Architect and Development Manager apparent discrepancies or defects in such other construction that would render it unsuitable for such proper execution and results. Failure of the Construction Manager Contractor so to so report shall constitute an acknowledgment that the Owner's or separate contractor's completed or partially completed construction is fit and proper to receive the Construction ManagerContractor's Work, except as to defects not then reasonably discoverable.
6.2.3 The Owner shall be reimbursed by the Construction Manager Contractor for costs incurred by the Owner which are payable to a separate contractor because of delays, improperly timed activities or defective construction of the Construction ManagerContractor. The Owner shall be responsible to the Contractor for costs incurred by the Contractor because of delays, improperly timed activities, damage to the Work or defective construction of a separate contractor.
6.2.4 The Construction Manager Contractor shall promptly remedy damage wrongfully caused by the Construction Manager Contractor to completed or partially completed construction or to property of the Owner or separate contractors as provided in Subparagraph 10.2.5.
6.2.5 The Owner and each separate contractor shall have the same responsibilities for cutting and patching as are described for the Construction Manager Contractor in Paragraph Subparagraph 3.14.
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Contractor (Corixa Corp)
MUTUAL RESPONSIBILITY. 6.2.1 The Construction Manager Contractor shall afford the Owner and separate contractors reasonable opportunity for introduction and storage of their materials and equipment and performance of their activities activities, and shall connect and coordinate the Construction Manager's Contractor’s construction and operations with theirs as required by the Contract Documents.
6.2.2 If part of the Construction Manager's Contractor’s Work depends for proper execution or results upon construction or operations by the Owner or a separate contractor, the Construction Manager Contractor shall, prior to proceeding with that portion of the Work, promptly report to the Owner and Architect and Development Manager apparent discrepancies or defects in such other construction that would render it unsuitable for such proper execution and results. Failure of the Construction Manager Contractor so to so report shall constitute an acknowledgment that the Owner's ’s or separate contractor's ’s completed or partially completed construction is fit and proper to receive the Construction Manager's Contractor’s Work, except as to defects not then reasonably discoverable.
6.2.3 The Owner shall be reimbursed by the Construction Manager Contractor for costs incurred by the Owner which are payable to a separate contractor because of delays, improperly timed activities or defective construction of the Construction ManagerContractor. The Owner shall be responsible to the Contractor for costs incurred by the Contractor because of delays, improperly timed activities, damage to the Work or defective construction of a separate contractor.
6.2.4 The Construction Manager Contractor shall promptly remedy damage wrongfully caused by the Construction Manager Contractor to completed or partially completed construction or to property of the Owner or separate contractors as provided in Subparagraph 10.2.5.
6.2.5 The Owner and each separate contractor shall have the same responsibilities for cutting and patching as are described for the Construction Manager Contractor in Paragraph Subparagraph 3.14.
Appears in 1 contract
Sources: Construction Contract
MUTUAL RESPONSIBILITY. 6.2.1 The Construction Manager Contractor shall afford the Owner and separate contractors Contractors reasonable opportunity for introduction and storage of their materials and equipment and performance of their activities and shall connect and coordinate the Construction ManagerContractor's construction and operations with theirs as required by the Contract Documents.
6.2.2 If part of the Construction ManagerContractor's Work depends for proper execution or results upon construction or operations by the Owner or a separate contractor, the Construction Manager Contractor shall, prior to proceeding with that portion of the Work, promptly report to the Architect and Development Manager apparent discrepancies or defects in such other construction that would render it unsuitable for such proper execution and results. Failure of the Construction Manager Contractor to so report shall constitute an acknowledgment that the Owner's or separate contractor's completed contractors' completed, or partially completed construction construction, is fit and proper to receive the Construction ManagerContractor's Work, except as to defects not then reasonably discoverable.
6.2.3 The Owner shall be reimbursed by the Construction Manager Contractor for costs incurred by the Owner which are payable to a separate contractor because of delays, improperly timed activities or defective construction of the Construction ManagerContractor. The Owner shall be responsible to the Contractor for costs incurred by the Contractor because of delays, improperly timed activities, and damage to the Work or defective construction of a separate contractor.
6.2.4 The Construction Manager Contractor shall promptly remedy damage wrongfully caused by the Construction Manager Contractor to completed or partially completed construction or to property of the Owner or separate contractors as provided in Subparagraph 10.2.5.
6.2.5 The Owner and each separate contractor shall have the same responsibilities for cutting and patching as are described for the Construction Manager Contractor in Paragraph 3.14.
Appears in 1 contract
Sources: Architectural Services Agreement
MUTUAL RESPONSIBILITY. 6.2.1 The Construction Manager shall afford the Owner and separate contractors reasonable opportunity for introduction and storage of their materials and equipment and performance of their activities and shall connect and coordinate the Construction Manager's construction and operations with theirs as required by the Contract Documents.
6.2.2 If part of the Construction Manager's Work depends for proper execution or results upon construction or operations by the Owner or a separate contractor, the Construction Manager shall, prior to proceeding with that portion of the Work, promptly report to the Architect and Development Manager Design Professional apparent discrepancies or defects in such other construction that would render it unsuitable for such proper execution and results. Failure of the Construction Manager to so report shall constitute an acknowledgment that the Owner's or separate contractor's completed Contractors' completed, or partially completed construction construction, is fit and proper to receive the Construction Manager's Work, except as to defects not then reasonably discoverable.
6.2.3 The Owner shall be reimbursed by the Construction Manager for costs incurred by the Owner which are payable to a separate contractor because of delays, improperly timed activities or defective construction of the Construction Manager. The Owner shall be responsible to the Construction Manager for costs incurred by the Construction Manager because of delays, improperly timed activities, and damage to the Work or defective construction of a separate contractor.
6.2.4 The Construction Manager shall promptly remedy damage wrongfully caused by the Construction Manager to completed or partially completed construction or to property of the Owner or separate contractors as provided in Subparagraph Subsection 10.2.5.
6.2.5 The Owner and each separate contractor shall have the same responsibilities for cutting and patching as are described for the Construction Manager in Paragraph Section 3.14.
Appears in 1 contract
MUTUAL RESPONSIBILITY. 6.2.1 The Construction Manager Contractor shall afford the Owner and separate contractors reasonable opportunity for introduction and storage of their materials and equipment and performance of their activities and shall connect and coordinate the Construction ManagerContractor's construction and operations with theirs as required by the Contract Documents.
6.2.2 If part of the Construction ManagerContractor's Work depends for proper execution or results upon construction or operations by the Owner or a separate contractor, the Construction Manager Contractor shall, prior to proceeding with that portion of the Work, promptly report to the Architect and Development Manager Owner apparent discrepancies or defects in such other construction that would render it unsuitable for such proper execution and results. Failure of the Construction Manager Contractor so to so report shall constitute an acknowledgment that the Owner's or separate contractor's completed or 35 partially completed construction is fit and proper to receive the Construction ManagerContractor's Work, except as to defects not then reasonably discoverable.
6.2.3 The Owner shall be reimbursed by the Construction Manager Contractor for costs incurred by the Owner which are payable to a separate contractor because of delays, improperly timed activities or defective construction of the Construction Manager.Contractor. The Owner shall be responsible to the
6.2.4 The Construction Manager Contractor shall promptly remedy damage wrongfully caused by the Construction Manager Contractor to completed or partially completed construction or to property of the Owner or separate contractors as provided in Subparagraph 10.2.5.. 45
6.2.5 The Owner and each separate contractor shall have the same responsibilities for cutting and patching as are described for the Construction Manager Contractor in Paragraph 3.14.
Appears in 1 contract
Sources: General Conditions of the Contract for Construction
MUTUAL RESPONSIBILITY. 6.2.1 The Construction Manager Contractor shall afford the Owner and separate contractors contractors’ reasonable opportunity for introduction and storage of their materials and equipment and performance of their activities activities, and shall connect and coordinate the Construction ManagerContractor's construction and operations with theirs as required by the Contract Documents.
6.2.2 If part of the Construction ManagerContractor's Work depends for on proper execution or results upon construction or operations by the Owner or a separate contractor, the Construction Manager Contractor shall, prior to proceeding with that portion of the Work, promptly report to the Architect Design Professional and Development Manager Owner apparent discrepancies or defects in such other construction that would render it unsuitable for such proper execution and results. Failure of the Construction Manager Contractor to so report shall constitute an acknowledgment that the Owner's or separate contractor's ’s completed or partially completed construction is fit and proper to receive the Construction ManagerContractor's Work, except as to defects not then reasonably discoverable.
6.2.3 The Owner shall be reimbursed by the Construction Manager Contractor for costs incurred by the Owner which are payable to a separate contractor because of delays, improperly timed activities or defective construction of the Construction ManagerContractor. The Owner shall be responsible to the Contractor for costs incurred by the Contractor because of delays, improperly timed activities and damage to the Work or defective construction of the Owner or a separate Owner contractor. Should the Contractor sustain any personal injury or damage to property through any act or omission of any other Contractor having a contract with the Owner, the Contractor sustaining damage will have no claim or cause of action against the Owner for such damage and hereby waives any such claim.
6.2.4 The Construction Manager Contractor shall promptly remedy damage wrongfully caused by the Construction Manager Contractor to completed or partially completed or existing construction or to property of the Owner or separate contractors as provided in Subparagraph 10.2.5.
6.2.5 The Owner and each separate contractor shall have the same responsibilities for cutting and patching as are described for the Construction Manager Contractor in Paragraph Subparagraph 3.14.
Appears in 1 contract
MUTUAL RESPONSIBILITY. 6.2.1 The Construction Manager Contractor shall afford the Owner and separate contractors reasonable opportunity for introduction and storage of their materials and equipment and performance of their activities activities, and shall connect and coordinate the Construction Manager's Contractor’s construction and operations with theirs as required by the Contract Documents.
6.2.2 If part of the Construction Manager's Contractor’s Work depends for proper execution or results upon construction or operations by the Owner or a separate contractor, the Construction Manager Contractor shall, prior to proceeding with that portion of the Work, promptly report to the Architect and Development Manager apparent discrepancies or defects in such other construction that would render it unsuitable for such proper execution and results. Failure of the Construction Manager Contractor so to so report shall constitute an acknowledgment that the Owner's ’s or separate contractor's ’s completed or partially completed construction is fit and proper to receive the Construction Manager's Contractor’s Work, except as to defects not then reasonably discoverable.
6.2.3 The Owner Contractor shall be reimbursed by the Construction Manager pay for costs incurred by the Owner which are payable to a separate contractor because of delays, improperly timed activities or defective construction of the Construction ManagerContractor. Such separate contractor shall be responsible to the Contractor for costs incurred by the Contractor because of delays, improperly timed activities, damage to the Work or defective construction of the separate contractor.
6.2.4 The Construction Manager Contractor shall promptly remedy damage wrongfully caused by the Construction Manager Contractor to completed or partially completed construction or to property of the Owner or separate contractors as provided in Subparagraph 10.2.5contractors.
6.2.5 The Owner and each separate contractor shall have the same responsibilities for cutting and patching as are described for the Construction Manager in Paragraph 3.14.
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Contractor (Adicet Bio, Inc.)